[2012] KEHC 4770 (KLR)

[2012] KEHC 4770 (KLR)

The court found that the defendant failed to honour his professional undertaking to pay Kshs.5 million within 45 days, necessitating the plaintiff to file suit and incur costs. The defendant only settled the principal sum after significant delay, resulting in the accrual of interest. The court held that the...

Source-derived case information.

Citation
[2012] KEHC 4770 (KLR)
Parties
Plaintiff: Industrial and Commercial Development Corporation; Defendant: Evans A. Ongicho Advocate
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 691 of 2010
Procedural Posture
Civil Case / Ruling on Interest and Costs After Settlement of Principal Sum
Outcome
Application for interest and costs allowed.
Judges
DK Musinga
Legal Topics
Professional Undertakings, Enforcement of Undertakings, Award of Interest, Award of Costs
Source Language
en
Commercial and Corporate Civil Procedure Professional Undertakings Enforcement of Undertakings Award of Interest Award of Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Industrial and Commercial Development Corporation

Plaintiff

Evans A. Ongicho Advocate

Defendant

Procedural Posture

Civil Case / Ruling on Interest and Costs After Settlement of Principal Sum

  1. 1 Whether the plaintiff is entitled to interest on the principal sum due to late honouring of a professional undertaking by the defendant.
  2. 2 Whether the plaintiff is entitled to the costs of the suit after the defendant settled the principal sum late.

Ratio Decidendi

The court found that the defendant failed to honour his professional undertaking to pay Kshs.5 million within 45 days, necessitating the plaintiff to file suit and incur costs. The defendant only settled the principal sum after significant delay, resulting in the accrual of interest. The court held that the plaintiff was entitled to interest at court rates (14% per annum) from 10th May, 2010 until payment in full, as well as the costs of the suit. The defendant's explanations regarding his client's failure to provide funds were deemed irrelevant to the determination of interest and costs, as the professional undertaking was binding and unconditional. The court exercised its discretion...

Court Disposition

Application for interest and costs allowed.

Orders

  • The defendant shall pay interest at court rates, being 14% per annum, from 10th May, 2010 until payment in full.
  • The defendant shall bear the costs of the suit.