[2013] KEHC 35 (KLR)

[2013] KEHC 35 (KLR)

The court found that the parties had reached a stalemate regarding the joint valuation of works under the Agreement, particularly concerning the demonstration and valuation of the software component. The Plaintiff argued that the software could not be valued without bringing in additional equipment, while the...

Source-derived case information.

Citation
[2013] KEHC 35 (KLR)
Parties
Plaintiff: Integrated CCTV Security Ltd.; Defendant: Kenya Airports Authority
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 590 of 2012
Procedural Posture
Civil Suit / Ruling on Application for Review and Enlargement of Time
Outcome
Application for review and enlargement of time temporarily allowed; site visit ordered; costs reserved.
Legal Topics
Contract Termination, Tender Disputes, Injunctive Relief, Valuation of Works
Source Language
en
Commercial and Corporate Civil Procedure Contract Termination Tender Disputes Injunctive Relief Valuation of Works

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Integrated CCTV Security Ltd.

Plaintiff

Kenya Airports Authority

Defendant

Procedural Posture

Civil Suit / Ruling on Application for Review and Enlargement of Time

  1. 1 Whether the court should review and enlarge the time for filing a joint valuation report pursuant to the Agreement between the parties.
  2. 2 Whether the Plaintiff should be allowed to bring additional equipment on site to demonstrate the software component of the contract.
  3. 3 Whether the Orders sought by the Plaintiff fall outside the prayers of the Plaint.

Ratio Decidendi

The court found that the parties had reached a stalemate regarding the joint valuation of works under the Agreement, particularly concerning the demonstration and valuation of the software component. The Plaintiff argued that the software could not be valued without bringing in additional equipment, while the Defendant objected on the basis that such equipment was not supplied under the contract. The court noted that both parties agreed a site visit by the court, assisted by a technical expert, would be the most effective way to resolve the impasse. Exercising its inherent jurisdiction, the court temporarily extended the time for review of its previous Order and for the valuation of...

Court Disposition

Application for review and enlargement of time temporarily allowed; site visit ordered; costs reserved.

Orders

  • Time for review of the court's Order dated 11 October 2012 is temporarily extended.
  • Time for valuation of works pursuant to the Agreement is enlarged for up to 14 days after the court's site visit.