[2017] KEELC 1024 (KLR)

[2017] KEELC 1024 (KLR)

The court found that the requirements for public participation under the Constitution and the Environmental Management and Co-ordination Act were substantially met. The Association and other stakeholders were informed of the project, given opportunities to comment, and their concerns were addressed. The absence of...

Source-derived case information.

Citation
[2017] KEELC 1024 (KLR)
Parties
Appellant: Isaac Gitoho, Peter Mangi and Sanjeev Sharma (Suing as officials of The Runda Association); Respondent: The Director General, NEMA; Respondent: The Grove Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 50 of 2016
Procedural Posture
Environmental Appeal / Judgment
Outcome
appeal dismissed
Legal Topics
Environmental Impact Assessment, Public Participation, Wetlands Determination, Statutory Compliance, Licensing Procedure
Source Language
en
Environmental Law Land and Property Environmental Impact Assessment Public Participation Wetlands Determination Statutory Compliance Licensing Procedure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Isaac Gitoho, Peter Mangi and Sanjeev Sharma (Suing as officials of The Runda Association)

Appellant

The Director General, NEMA

Respondent

The Grove Limited

Respondent

Procedural Posture

Environmental Appeal / Judgment

  1. 1 Whether there was meaningful public participation in the EIA process as required by law.
  2. 2 Whether the project site was a wetland or floodplain requiring special protection under environmental laws.
  3. 3 Whether non-compliance with certain procedural requirements (e.g., radio announcements, number of meetings) invalidated the EIA licence.

Ratio Decidendi

The court found that the requirements for public participation under the Constitution and the Environmental Management and Co-ordination Act were substantially met. The Association and other stakeholders were informed of the project, given opportunities to comment, and their concerns were addressed. The absence of radio announcements and the failure to hold multiple meetings did not invalidate the process, as the affected persons were otherwise adequately informed. The evidence, including expert testimony and site visits, established that the project site was not a wetland and that there was no stream originating from the land in question. The Tribunal properly analyzed the evidence and...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed in its entirety.
  • Each party to bear its own costs.