[2014] KEHC 3236 (KLR)

[2014] KEHC 3236 (KLR)

The plaintiffs failed to establish a prima facie case for the grant of a temporary injunction. They did not provide sufficient evidence to prove that the disputed road is private or that they have proprietary rights over it. The survey map presented indicates the road serves multiple parcels and does not support the...

Source-derived case information.

Citation
[2014] KEHC 3236 (KLR)
Parties
Plaintiff: Isaac Nunda Nyabayo; Plaintiff: Annah Bosibori Isaac; Plaintiff: Clemencia Nyaboke Onyancha; Defendant: The County Government of Kisii; Defendant: Hon. James Ongwae
Court
High Court
Court Station
High Court at Kisii
Jurisdiction
Kenya
Case Number
Environment & Land Case 106 of 2014
Procedural Posture
Environment and Land Civil Case / Ruling on Interlocutory Injunction and Preliminary Objection
Outcome
Plaintiffs' application for temporary injunction dismissed with costs to the defendants. Limited protective order granted against further damage.
Legal Topics
Injunctive Relief, Compulsory Acquisition, Public Vs Private Land, Burden of Proof
Source Language
en
Land and Property Civil Procedure Injunctive Relief Compulsory Acquisition Public Vs Private Land Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Isaac Nunda Nyabayo

Plaintiff

Annah Bosibori Isaac

Plaintiff

Clemencia Nyaboke Onyancha

Plaintiff

The County Government of Kisii

Defendant

Hon. James Ongwae

Defendant

Procedural Posture

Environment and Land Civil Case / Ruling on Interlocutory Injunction and Preliminary Objection

  1. 1 Whether the plaintiffs have established a prima facie case for grant of a temporary injunction against the defendants.
  2. 2 Whether the road in dispute is a private or public road and whether the plaintiffs have proprietary rights over it.
  3. 3 Whether the defendants followed due process in upgrading or constructing the road.

Ratio Decidendi

The plaintiffs failed to establish a prima facie case for the grant of a temporary injunction. They did not provide sufficient evidence to prove that the disputed road is private or that they have proprietary rights over it. The survey map presented indicates the road serves multiple parcels and does not support the claim of exclusivity or private status. The plaintiffs also failed to demonstrate that the damage to their properties was occasioned wrongfully by the defendants, as the works were carried out by an independent contractor and the status of the road remains undetermined. Since the plaintiffs came to court after much of the alleged damage had already occurred, the court found no...

Court Disposition

Plaintiffs' application for temporary injunction dismissed with costs to the defendants. Limited protective order granted against further damage.

Orders

  • The plaintiffs' application dated 14th March 2014 is dismissed with costs to the defendants.
  • The defendants shall not interfere with or cause any other or further destruction or damage to the developments and/or structures on the suit properties pending the hearing and determination of this suit.