[2015] KEHC 6717 (KLR)

[2015] KEHC 6717 (KLR)

The court found that the contract between the parties expressly provided for the consequences of termination, including the contractor's obligation to vacate the site and the employer's right to engage new contractors. The applicant failed to apply for an extension of time as required, and upon termination,...

Source-derived case information.

Citation
[2015] KEHC 6717 (KLR)
Parties
Plaintiff: Itabuild Imports Limited; Defendant: A.I.C Kijabe Hospital
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 582 of 2014
Procedural Posture
Civil Application / Ruling on Interim Injunction Pending Arbitration
Outcome
application dismissed
Judges
DO Ogembo
Legal Topics
Construction Contracts, Termination of Contracts, Arbitration Interim Measures, Performance Bonds
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Termination of Contracts Arbitration Interim Measures Performance Bonds

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Itabuild Imports Limited

Plaintiff

A.I.C Kijabe Hospital

Defendant

Procedural Posture

Civil Application / Ruling on Interim Injunction Pending Arbitration

  1. 1 Whether the court should grant interim injunctions restraining the defendant from continuing works or appointing new contractors pending arbitration.
  2. 2 Whether the termination of the contract by the defendant was lawful and its effect on the parties' rights.
  3. 3 Whether the applicant is entitled to interim measures of protection under Section 7 of the Arbitration Act.

Ratio Decidendi

The court found that the contract between the parties expressly provided for the consequences of termination, including the contractor's obligation to vacate the site and the employer's right to engage new contractors. The applicant failed to apply for an extension of time as required, and upon termination, acquiesced to vacating the site and removing its property. The arbitration clause did not stipulate that works must cease during arbitration, and granting the interim injunction sought would contradict the clear terms of the contract, effectively rewriting the parties' agreement. The applicant's claim is essentially for damages, which are an adequate remedy if the arbitrator finds in...

Court Disposition

application dismissed

Orders

  • The Plaintiff's/Applicant's Chamber Summons application dated 9th December 2014 is dismissed for lack of merit.
  • The Defendant/Respondent is directed to comply with Clauses 38.4.2 and 38.4.3 of the contract, if not already done, within 30 days from the date hereof.