[2015] KEHC 8149 (KLR)

[2015] KEHC 8149 (KLR)

The court held that it had jurisdiction under Section 7(1) of the Arbitration Act to grant interim relief to preserve the subject matter of the dispute pending arbitration. The existence of a valid arbitration clause in the contract between the plaintiff and the 1st defendant was not disputed, and the dispute...

Source-derived case information.

Citation
[2015] KEHC 8149 (KLR)
Parties
Plaintiff: Italbuild Imports Limited; Defendant: A.I.C Kijabe Hospital; Defendant: Imperial Bank Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 407 of 2014
Procedural Posture
Civil Suit / Ruling on Interlocutory Applications for Interim Relief and Injunction Pending Arbitration
Outcome
Plaintiff's application for interim relief allowed; 1st defendant's application dismissed.
Judges
CM Kamau
Legal Topics
Performance Bonds, Interim Measures, Arbitration Clauses, Injunctive Relief, Contractual Disputes, Construction Contracts
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Performance Bonds Interim Measures Arbitration Clauses Injunctive Relief Contractual Disputes +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Italbuild Imports Limited

Plaintiff

A.I.C Kijabe Hospital

Defendant

Imperial Bank Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Interlocutory Applications for Interim Relief and Injunction Pending Arbitration

  1. 1 Whether the High Court has jurisdiction to grant interim relief pending arbitration under Section 7 of the Arbitration Act.
  2. 2 Whether the plaintiff is entitled to an injunction restraining the 2nd defendant from honouring the performance bond demand by the 1st defendant pending arbitration.
  3. 3 Whether the performance bond is separable from the underlying contract or subject to the arbitration clause.

Ratio Decidendi

The court held that it had jurisdiction under Section 7(1) of the Arbitration Act to grant interim relief to preserve the subject matter of the dispute pending arbitration. The existence of a valid arbitration clause in the contract between the plaintiff and the 1st defendant was not disputed, and the dispute regarding alleged default and entitlement to the performance bond was within the arbitrator's jurisdiction. The court found that the performance bond, although a separate contract, was not wholly independent of the underlying contract, and its forfeiture depended on whether the plaintiff was in default—a matter for arbitration. The court concluded that the plaintiff had demonstrated...

Court Disposition

Plaintiff's application for interim relief allowed; 1st defendant's application dismissed.

Orders

  • An injunction is issued restraining the 2nd defendant from honouring the demand by the 1st defendant dated 17th September 2014 or any other demand pending arbitration.
  • An injunction is issued prohibiting the 1st defendant from making further demands for payment of Performance Bond Ref. No. LG NO 929/SEP/12 from the 2nd defendant pending arbitration.