[2015] KEHC 7355 (KLR)

[2015] KEHC 7355 (KLR)

The court found that the respondent had not complied with the judgment and orders issued on 11/3/2011 regarding the division and transfer of matrimonial property and payment of rental proceeds. The respondent's challenge to the applicant's valuation was noted, but he had not participated in the valuation process nor...

Source-derived case information.

Citation
[2015] KEHC 7355 (KLR)
Parties
Applicant: J B N; Respondent: M O N
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 81 of 2003
Procedural Posture
Civil Suit / Post Judgment Enforcement Application
Outcome
Application allowed with costs to the applicant.
Judges
AO Muchelule, LA Achode
Legal Topics
Matrimonial Property Division, Enforcement of Judgment, Valuation of Property
Source Language
en
Family and Children Civil Procedure Matrimonial Property Division Enforcement of Judgment Valuation of Property

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

J B N

Applicant

M O N

Respondent

Procedural Posture

Civil Suit / Post Judgment Enforcement Application

  1. 1 Whether the respondent has complied with the court's judgment and orders regarding division and transfer of matrimonial property.
  2. 2 Whether the applicant is entitled to enforcement of the judgment, including payment of rental proceeds and transfer of property shares.
  3. 3 Whether the respondent is entitled to a stay of execution pending appeal.

Ratio Decidendi

The court found that the respondent had not complied with the judgment and orders issued on 11/3/2011 regarding the division and transfer of matrimonial property and payment of rental proceeds. The respondent's challenge to the applicant's valuation was noted, but he had not participated in the valuation process nor sought a formal stay of execution. The court held that, in the absence of a stay, there was no legal impediment to enforcing the judgment. To ensure fairness, the court ordered that the parties agree on an independent valuer within 15 days to value the properties in accordance with the judgment, failing which the court would appoint a valuer at the respondent's cost. The...

Court Disposition

Application allowed with costs to the applicant.

Orders

  • Within 15 days, parties to agree on a valuer to value the properties in question in terms of the judgment.
  • If parties do not agree, the court shall appoint a valuer whose fees shall be paid by the respondent.