[2013] KEHC 2783 (KLR)

[2013] KEHC 2783 (KLR)

The court found that the plaintiff had established a prima facie case with a high probability of success by demonstrating it held a valid wayleave and that the defendants breached the mandatory requirements of section 27 of the Kenya Roads Act by failing to issue a written statutory notice and allow reasonable time...

Source-derived case information.

Citation
[2013] KEHC 2783 (KLR)
Parties
Plaintiff: Jamii Telecommunication Ltd; Defendant: Kenya Urban Roads Authority; Defendant: Mattan Contractors Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Environment & Land Case 910 of 2012
Procedural Posture
Environment and Land Case / Ruling on Interlocutory Injunction Application
Outcome
Application allowed in terms of prayers 3, 4, and 6; costs in the cause.
Judges
LN Gacheru
Legal Topics
Wayleave Rights, Injunctive Relief, Statutory Notice Requirements, Infrastructure Utilities, Road Reserve Disputes
Source Language
en
Land and Property Civil Procedure Wayleave Rights Injunctive Relief Statutory Notice Requirements Infrastructure Utilities Road Reserve Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Jamii Telecommunication Ltd

Plaintiff

Kenya Urban Roads Authority

Defendant

Mattan Contractors Limited

Defendant

Procedural Posture

Environment and Land Case / Ruling on Interlocutory Injunction Application

  1. 1 Whether the defendants failed to issue the statutory notice required under section 27 of the Kenya Roads Act before interfering with the plaintiff's infrastructure utilities.
  2. 2 Whether the plaintiff is entitled to a temporary injunction restraining the defendants from further interference or destruction of its infrastructure utilities.
  3. 3 Whether the balance of convenience and irreparable harm favor the grant of injunctive relief to the plaintiff.

Ratio Decidendi

The court found that the plaintiff had established a prima facie case with a high probability of success by demonstrating it held a valid wayleave and that the defendants breached the mandatory requirements of section 27 of the Kenya Roads Act by failing to issue a written statutory notice and allow reasonable time for relocation of the infrastructure utilities. The court rejected the defendants' argument that stakeholder meetings constituted sufficient notice, holding that the law requires written notice. The court further held that the plaintiff had shown it would suffer irreparable loss not compensable by damages due to the destruction of essential infrastructure and disruption of...

Court Disposition

Application allowed in terms of prayers 3, 4, and 6; costs in the cause.

Orders

  • Defendants are restrained from interfering with, obstructing, or damaging the plaintiff’s infrastructure utilities laid upon and along the specified roads in Upper Hill, Nairobi, pending determination of the suit.
  • Defendants are compelled to issue the requisite statutory notice as required under section 27 of the Kenya Roads Act, 2007, and to avail to the plaintiff the program of works as agreed at the stakeholders meeting of 2nd October, 2012, to allow reasonable time for mitigation measures.