[2021] KEHC 4520 (KLR)

[2021] KEHC 4520 (KLR)

The court found that while the principal contractual sum was paid during the pendency of the suit, the defendant's delay in payment was unreasonable, deliberate, and unjustified, given that the contracts were budgeted for and approved. The delay, which extended up to three years, was found to be high-handed and...

Source-derived case information.

Citation
[2021] KEHC 4520 (KLR)
Parties
Plaintiff: Jamuto Enterprises Limited (Suing through John Mutua M’Ruguru); Defendant: The County Government of Meru
Court
High Court
Court Station
High Court at Meru
Jurisdiction
Kenya
Case Number
Civil Suit 2 of 2020
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff awarded general damages for breach of contract; other claims dismissed.
Judges
CA Otieno
Legal Topics
Breach of Contract, Delay in Payment, General Damages, Special Damages, Interest on Loans
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Delay in Payment General Damages Special Damages Interest on Loans

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Jamuto Enterprises Limited (Suing through John Mutua M’Ruguru)

Plaintiff

The County Government of Meru

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the plaintiff is entitled to general damages for breach of contract due to delayed payment by the defendant.
  2. 2 Whether the plaintiff is entitled to damages for loss of business and mesne profits.
  3. 3 Whether the plaintiff is entitled to interest accrued on the Dhabiti Sacco loan.

Ratio Decidendi

The court found that while the principal contractual sum was paid during the pendency of the suit, the defendant's delay in payment was unreasonable, deliberate, and unjustified, given that the contracts were budgeted for and approved. The delay, which extended up to three years, was found to be high-handed and oppressive, causing the plaintiff financial hardship, including the forced sale of assets to service loans. Although general damages are not typically awarded for breach of contract, the court held that the circumstances justified an exception due to the defendant's conduct. However, the plaintiff failed to strictly prove special damages for loss of business or interest on the...

Court Disposition

Plaintiff awarded general damages for breach of contract; other claims dismissed.

Orders

  • Plaintiff awarded Kshs 6,000,000 as general damages for breach of contract.
  • Plaintiff awarded interest at court rates from the date of suit.