[2018] KEHC 6230 (KLR)

[2018] KEHC 6230 (KLR)

The court found that the defendant, as a professional contractor, bore the primary responsibility for ensuring that all legal requirements, including obtaining city council permission for the construction of the septic tank, were met. Although the plaintiff, as the property owner, had some responsibility, he was...

Source-derived case information.

Citation
[2018] KEHC 6230 (KLR)
Parties
Appellant: Japheth Arthur Mwangi; Respondent: Victory Construction
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Appeal 27 & 43 of 2014
Procedural Posture
Civil Appeal / Judgment
Outcome
Plaintiff's appeal allowed as to costs; defendant's appeal dismissed; apportionment of liability at 70% defendant, 30% plaintiff upheld.
Judges
A Mbogholi-Msagha
Legal Topics
Breach of Contract, Apportionment of Liability, Construction Disputes, Professional Duty of Care
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Apportionment of Liability Construction Disputes Professional Duty of Care

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Japheth Arthur Mwangi

Appellant

Victory Construction

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the defendant breached the construction contract with the plaintiff.
  2. 2 Whether liability for the illegality of constructing a septic tank without city council permission should be apportioned between the parties.
  3. 3 Whether the trial court erred in apportioning liability at 70% to the defendant and 30% to the plaintiff.

Ratio Decidendi

The court found that the defendant, as a professional contractor, bore the primary responsibility for ensuring that all legal requirements, including obtaining city council permission for the construction of the septic tank, were met. Although the plaintiff, as the property owner, had some responsibility, he was entitled to rely on the defendant's expertise and advice. The evidence showed that the defendant offered professional advice but ultimately proceeded with the works despite the lack of permission, constituting a breach of contract. The trial court's apportionment of liability—70% to the defendant and 30% to the plaintiff—was upheld as reasonable given the circumstances. The...

Court Disposition

Plaintiff's appeal allowed as to costs; defendant's appeal dismissed; apportionment of liability at 70% defendant, 30% plaintiff upheld.

Orders

  • Respondent's (defendant's) appeal No. 43 of 2014 is dismissed in its entirety.
  • Appellant's (plaintiff's) appeal No. 27 of 2014 is allowed with costs as stated.