[2014] KEELC 240 (KLR)

[2014] KEELC 240 (KLR)

The court found that clause 3 (10) of the lease agreement did not provide for renewal of the lease but only for a deduction of Kshs.100,000 from the contract sum if the applicant could not complete the project within the contract period due to certain reasons. There was no contractual basis for compelling renewal....

Source-derived case information.

Citation
[2014] KEELC 240 (KLR)
Parties
Plaintiff: Jiangxi Zhongmei Engineering Construction Co. Ltd; Defendant: Dickson Makheti Muyundo
Court
Environment and Land Court
Court Station
Environment and Land Court at Kitale
Jurisdiction
Kenya
Case Number
Environment & Land Case 108 of 2014
Procedural Posture
Land Case / Ruling on Interlocutory Injunction Application
Outcome
application dismissed with costs to the respondent
Judges
EO Obaga
Legal Topics
Land Lease Disputes, Injunctive Relief, Breach of Contract, Interpretation of Contractual Clauses
Source Language
en
Land and Property Civil Procedure Land Lease Disputes Injunctive Relief Breach of Contract Interpretation of Contractual Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Jiangxi Zhongmei Engineering Construction Co. Ltd

Plaintiff

Dickson Makheti Muyundo

Defendant

Procedural Posture

Land Case / Ruling on Interlocutory Injunction Application

  1. 1 Whether the applicant is entitled to an interlocutory injunction restraining the respondent from interfering with the applicant's use and occupation of the suit land.
  2. 2 Whether clause 3 (10) of the lease agreement provided for renewal of the lease for a further term.
  3. 3 Whether the applicant will suffer irreparable injury not compensable by damages if the injunction is not granted.

Ratio Decidendi

The court found that clause 3 (10) of the lease agreement did not provide for renewal of the lease but only for a deduction of Kshs.100,000 from the contract sum if the applicant could not complete the project within the contract period due to certain reasons. There was no contractual basis for compelling renewal. The applicant failed to demonstrate a prima facie case with a probability of success, as the lease had expired and no renewal clause existed. Furthermore, the applicant did not prove that it would suffer irreparable injury not compensable by damages, as any loss relating to uncollected stones could be quantified. Consequently, the application for injunction lacked merit and was...

Court Disposition

application dismissed with costs to the respondent

Orders

  • The applicant's application for injunction is dismissed with costs to the respondent.