[2015] KEHC 2985 (KLR)

[2015] KEHC 2985 (KLR)

The court found that a valid and binding contract existed between the Plaintiff and the Defendant for the hire of construction equipment and vehicles. The Plaintiff provided uncontroverted evidence that it supplied the equipment and that the Defendant failed to pay the outstanding sum of Kshs 27,291,003.18. The...

Source-derived case information.

Citation
[2015] KEHC 2985 (KLR)
Parties
Plaintiff: Jomat Construction Limited; Defendant: Nyoro Construction Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 208 of 2012
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Plaintiff.
Judges
CM Kamau
Legal Topics
Contract Enforcement, Equipment Hire Disputes, Interest Awards, Burden of Proof
Source Language
en
Commercial and Corporate Civil Procedure Contract Enforcement Equipment Hire Disputes Interest Awards Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Jomat Construction Limited

Plaintiff

Nyoro Construction Company Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a valid and binding contract between the Plaintiff and the Defendant for the hire of construction equipment.
  2. 2 Whether the Defendant was liable to pay the Plaintiff the sum of Kshs 27,291,003.18.
  3. 3 What was the applicable rate of interest, if any, on the outstanding sum.

Ratio Decidendi

The court found that a valid and binding contract existed between the Plaintiff and the Defendant for the hire of construction equipment and vehicles. The Plaintiff provided uncontroverted evidence that it supplied the equipment and that the Defendant failed to pay the outstanding sum of Kshs 27,291,003.18. The Defendant, despite admitting the contract, did not adduce any oral or documentary evidence to rebut the Plaintiff's claim or prove payment of the alleged invoices. The court held that the Plaintiff had discharged its burden of proof, and the Defendant's failure to participate in the hearing or tender evidence meant the Plaintiff's case was unchallenged. Regarding interest, the...

Court Disposition

Judgment for the Plaintiff.

Orders

  • The Defendant shall pay the Plaintiff Kshs 27,291,003.18.
  • Interest on the sum of Kshs 27,291,003.18 at court rates from the date of filing suit until payment in full.