[2022] KEELC 1260 (KLR)

[2022] KEELC 1260 (KLR)

The court found that although the temporary injunction orders previously granted had lapsed and were not expressly extended, the principle of maintaining the status quo required that the plaintiff be allowed to continue mining activities as he had been doing prior to the dispute, pending the final determination of...

Source-derived case information.

Citation
[2022] KEELC 1260 (KLR)
Parties
Plaintiff: Joseph Kamau Mbiriri; Defendant: Robert Kiwua Kigo; Defendant: Agnes Ndunge Kiwua & Associates; Defendant: Gushumbu D.A. Rangaco Ltd
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case 423 of 2017
Procedural Posture
Land and Property Dispute / Ruling on Interpretation and Scope of Status Quo Orders Pending Full Hearing
Outcome
Status quo orders extended; plaintiff to continue mining pending hearing and determination; matter to be fast-tracked; each party to bear own costs.
Legal Topics
Mining Rights, Status Quo Orders, Injunctions, Land Ownership Disputes
Source Language
en
Land and Property Environmental Law Mining Rights Status Quo Orders Injunctions Land Ownership Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Joseph Kamau Mbiriri

Plaintiff

Robert Kiwua Kigo

Defendant

Agnes Ndunge Kiwua & Associates

Defendant

Gushumbu D.A. Rangaco Ltd

Defendant

Procedural Posture

Land and Property Dispute / Ruling on Interpretation and Scope of Status Quo Orders Pending Full Hearing

  1. 1 What is the interpretation, nature, meaning, and scope of the status quo order made by the court on 20th January, 2020.
  2. 2 How should the matter proceed pending the final determination of the suit.

Ratio Decidendi

The court found that although the temporary injunction orders previously granted had lapsed and were not expressly extended, the principle of maintaining the status quo required that the plaintiff be allowed to continue mining activities as he had been doing prior to the dispute, pending the final determination of the suit. The court invoked its inherent jurisdiction and relevant statutory provisions to extend the status quo orders, allowing the plaintiff to continue mining, and directed that the matter be fast-tracked for hearing and determination within ninety days. Each party was ordered to bear its own costs. The decision was grounded on the need to preserve the subject matter, ensure...

Court Disposition

Status quo orders extended; plaintiff to continue mining pending hearing and determination; matter to be fast-tracked; each party to bear own costs.

Orders

  • The status quo orders are extended, allowing the plaintiff to continue mining until the matter is heard and determined.
  • Section 37(1) and (3) of the Mining Act No.12 of 2016 to take effect, permitting the plaintiff to continue mining.