[2021] KEELRC 1881 (KLR)

[2021] KEELRC 1881 (KLR)

The court found that the respondent complied with the procedural requirements of the Employment Act, 2007 by informing the claimant of the allegations, providing opportunities for him to respond, and conducting a disciplinary hearing. Substantively, the respondent proved valid and fair reasons for dismissal,...

Source-derived case information.

Citation
[2021] KEELRC 1881 (KLR)
Parties
Claimant: Joshua Omenda Odeny; Respondent: Lake Victoria South Water Service Board
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Kisumu
Jurisdiction
Kenya
Case Number
Cause 184 of 2016
Procedural Posture
Employment Cause / Judgment
Outcome
claim dismissed with costs
Legal Topics
Unfair Termination, Procedural Fairness, Substantive Fairness, Breach of Contract, Disciplinary Process, Employee Entitlements
Source Language
en
Employment and Labour Unfair Termination Procedural Fairness Substantive Fairness Breach of Contract Disciplinary Process Employee Entitlements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Joshua Omenda Odeny

Claimant

Lake Victoria South Water Service Board

Respondent

Procedural Posture

Employment Cause / Judgment

  1. 1 Whether the claimant's suspension and subsequent dismissal were procedurally and substantively fair under the Employment Act, 2007.
  2. 2 Whether the respondent breached the claimant's contract by failing to pay salary, house allowance, and medical allowance during suspension.
  3. 3 Whether the claimant was entitled to any relief for alleged breach of contract.

Ratio Decidendi

The court found that the respondent complied with the procedural requirements of the Employment Act, 2007 by informing the claimant of the allegations, providing opportunities for him to respond, and conducting a disciplinary hearing. Substantively, the respondent proved valid and fair reasons for dismissal, including the claimant's failure to prepare and submit the required handover report and to attend the project handover, despite being the appointed Scheme Manager. The claimant's explanations for his conduct were unsubstantiated and lacked credibility. The claimant also failed to prove any breach of contract regarding salary, house allowance, or medical allowance during suspension, as...

Court Disposition

claim dismissed with costs

Orders

  • The entire cause is dismissed with costs to the respondent.