[2025] KEHC 3286 (KLR)

[2025] KEHC 3286 (KLR)

The court found that while the contract between the parties contains an arbitration clause requiring disputes to be referred to arbitration, both the Arbitration Act (Section 7) and the contract itself (Clause 28.7) expressly permit parties to seek interim measures of protection from the High Court. The court held...

Source-derived case information.

Citation
[2025] KEHC 3286 (KLR)
Parties
Applicant: Jr Miles Construction Ltd; Respondent: Bomi Engineering and Construction Limited; Respondent: Fidelity Shield Insurance Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit E460 of 2024
Procedural Posture
Civil Suit / Ruling on Preliminary Objection
Outcome
preliminary objection dismissed
Judges
PM Mulwa
Legal Topics
Arbitration Agreements, Interim Measures, Jurisdiction of High Court, Preliminary Objection, Contractual Disputes
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Agreements Interim Measures Jurisdiction of High Court Preliminary Objection Contractual Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Jr Miles Construction Ltd

Applicant

Bomi Engineering and Construction Limited

Respondent

Fidelity Shield Insurance Company Limited

Respondent

Procedural Posture

Civil Suit / Ruling on Preliminary Objection

  1. 1 Whether the High Court has jurisdiction to entertain the application despite the existence of an arbitration clause in the contract.
  2. 2 Whether the application for interim measures under Section 7(1) of the Arbitration Act is properly before the court.
  3. 3 Whether the preliminary objection challenging the court's jurisdiction is merited.

Ratio Decidendi

The court found that while the contract between the parties contains an arbitration clause requiring disputes to be referred to arbitration, both the Arbitration Act (Section 7) and the contract itself (Clause 28.7) expressly permit parties to seek interim measures of protection from the High Court. The court held that the existence of an arbitration agreement does not oust its jurisdiction to grant such interim relief, especially where arbitral proceedings have not yet commenced and the subject matter requires preservation. The preliminary objection, which challenged the court's jurisdiction on the basis of the arbitration clause, was therefore without merit. The court concluded that it...

Court Disposition

preliminary objection dismissed

Orders

  • The 1st Respondent's Notice of Preliminary Objection dated 24th June 2024 is dismissed.
  • There shall be no order as to costs.