[2000] KEHC 443 (KLR)

[2000] KEHC 443 (KLR)

The court found that the defendant disconnected the plaintiff's electricity supply based on an alleged undercharge that was disputed by the plaintiff, despite the plaintiff having paid all bills for the relevant period. The Electric Power Act only permits disconnection for undisputed arrears, and the defendant...

Source-derived case information.

Citation
[2000] KEHC 443 (KLR)
Parties
Plaintiff: Kalima Bakery Limited; Defendant: The Kenya Power & Lighting Co. Ltd.
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 1766 of ??
Procedural Posture
Civil Case / Interlocutory Application for Mandatory Injunction
Outcome
Mandatory injunction granted in favor of the plaintiff.
Legal Topics
Mandatory Injunctions, Breach of Contract, Electricity Supply Disputes, Interlocutory Relief
Source Language
en
Civil Procedure Commercial and Corporate Mandatory Injunctions Breach of Contract Electricity Supply Disputes Interlocutory Relief

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kalima Bakery Limited

Plaintiff

The Kenya Power & Lighting Co. Ltd.

Defendant

Procedural Posture

Civil Case / Interlocutory Application for Mandatory Injunction

  1. 1 Whether the plaintiff is entitled to a mandatory injunction for reconnection of electricity supply pending resolution of the disputed undercharge.
  2. 2 Whether the defendant lawfully disconnected electricity supply in light of the disputed arrears and statutory requirements.
  3. 3 Whether damages would be an adequate remedy in lieu of a mandatory injunction.

Ratio Decidendi

The court found that the defendant disconnected the plaintiff's electricity supply based on an alleged undercharge that was disputed by the plaintiff, despite the plaintiff having paid all bills for the relevant period. The Electric Power Act only permits disconnection for undisputed arrears, and the defendant failed to provide the requisite notice under Section 83. The court held that the defendant's actions were unlawful and oppressive, particularly given its monopolistic position, and that the plaintiff could not be compelled to accept damages in lieu of a mandatory injunction. The court exercised its inherent jurisdiction to grant a mandatory injunction at the interlocutory stage,...

Court Disposition

Mandatory injunction granted in favor of the plaintiff.

Orders

  • A mandatory injunction is issued directing the defendant to reconnect and reinstate the plaintiff's electricity supply at the plaintiff's premises.