[2017] KEHC 3914 (KLR)

[2017] KEHC 3914 (KLR)

The court found that the original contract dated 2/11/2007, which set the consultancy fees at 8.5% of the project cost plus VAT and disbursements, was never validly varied, substituted, or superseded by any subsequent agreement. The correspondence and meetings following the original contract did not result in a...

Source-derived case information.

Citation
[2017] KEHC 3914 (KLR)
Parties
Plaintiff: Kamau James Gitutho Njendu t/a Gitutho Associates; Plaintiff: Harry Njoroge Gakuya t/a Gakuya & Associates; Plaintiff: Maxcad Consulting Engineers Ltd; Plaintiff: Primeconsult Engineers Ltd; Defendant: Multiple ICD K Ltd; Defendant: Multiple Hauliers (EA) Ltd
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 521 of 2011
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiffs against the defendants jointly and severally for Kshs.219,170,713.00, interest at 14% per annum from 1/5/2010 until payment in full, and costs of the suit and counter-claim.
Judges
CA Otieno
Legal Topics
Contract Variation, Consultancy Fees, Professional Services Contracts, Joint and Several Liability, Counter Claims, Interest Awards
Source Language
en
Commercial and Corporate Civil Procedure Contract Variation Consultancy Fees Professional Services Contracts Joint and Several Liability Counter Claims Interest Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Kamau James Gitutho Njendu t/a Gitutho Associates

Plaintiff

Harry Njoroge Gakuya t/a Gakuya & Associates

Plaintiff

Maxcad Consulting Engineers Ltd

Plaintiff

Primeconsult Engineers Ltd

Plaintiff

Multiple ICD K Ltd

Defendant

Multiple Hauliers (EA) Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the contract dated 2/11/2007 was validly varied, substituted or superseded by a subsequent agreement.
  2. 2 What are the terms of the contract regarding scope of works, consultancy fees, and VAT?
  3. 3 What sums, if any, have been paid to the plaintiffs as consultants?

Ratio Decidendi

The court found that the original contract dated 2/11/2007, which set the consultancy fees at 8.5% of the project cost plus VAT and disbursements, was never validly varied, substituted, or superseded by any subsequent agreement. The correspondence and meetings following the original contract did not result in a binding variation, as there was no unequivocal acceptance of new terms and the parties did not reach consensus ad idem. The court held that the plaintiffs were entitled to the outstanding balance of consultancy fees as per the original contract, less amounts already paid. Both defendants were found jointly and severally liable, as the 2nd defendant benefited from the contract and...

Court Disposition

Judgment for the plaintiffs against the defendants jointly and severally for Kshs.219,170,713.00, interest at 14% per annum from 1/5/2010 until payment in full, and costs of the suit and counter-claim.

Orders

  • Defendants to pay plaintiffs jointly and severally the sum of Kshs.219,170,713.00 apportioned as: 1st plaintiff Kshs.87,668,285; 2nd plaintiff Kshs.51,307,863; 3rd plaintiff Kshs.50,919,712; 4th plaintiff Kshs.29,149,704.
  • Interest on the above sums at 14% per annum from 1/5/2010 until payment in full.