[2023] KEELC 17985 (KLR)

[2023] KEELC 17985 (KLR)

The court found that although the 3rd defendant denied responsibility for the erection of the power lines, there was uncertainty as to which defendant was liable, with the 1st and 2nd defendants also distancing themselves from the impugned power lines. The presence of the 3rd defendant was deemed necessary to enable...

Source-derived case information.

Citation
[2023] KEELC 17985 (KLR)
Parties
Plaintiff: Christopher Kanai Kamau; Plaintiff: Mary Wangari Kanai; Defendant: Kenya Railways Corporation; Defendant: Construction Company Limited; Defendant: Kenya Power And Lighting Company
Court
Environment and Land Court
Court Station
Environment and Land Court at Nakuru
Jurisdiction
Kenya
Case Number
Environment & Land Case 23 of 2022
Procedural Posture
Environment and Land Case / Ruling on Notice of Motion to Strike Out 3rd Defendant for Misjoinder
Outcome
application dismissed with costs
Judges
FM Njoroge
Legal Topics
Misjoinder of Parties, Striking Out Pleadings, Electricity Wayleaves, Necessary Parties, Trespass to Land
Source Language
en
Civil Procedure Land and Property Misjoinder of Parties Striking Out Pleadings Electricity Wayleaves Necessary Parties Trespass to Land

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2
Sign in to unlock

Parties

Christopher Kanai Kamau

Plaintiff

Mary Wangari Kanai

Plaintiff

Kenya Railways Corporation

Defendant

Construction Company Limited

Defendant

Kenya Power And Lighting Company

Defendant

Procedural Posture

Environment and Land Case / Ruling on Notice of Motion to Strike Out 3rd Defendant for Misjoinder

  1. 1 Whether the 3rd defendant should be struck out from the suit for misjoinder.
  2. 2 Whether the pleadings disclose a reasonable cause of action against the 3rd defendant.

Ratio Decidendi

The court found that although the 3rd defendant denied responsibility for the erection of the power lines, there was uncertainty as to which defendant was liable, with the 1st and 2nd defendants also distancing themselves from the impugned power lines. The presence of the 3rd defendant was deemed necessary to enable the court to determine the real issues in controversy, particularly as to who erected the power lines on the plaintiffs' property. Striking out the 3rd defendant at this stage would be premature and could prejudice the fair determination of the matter. Therefore, the application to strike out the 3rd defendant for misjoinder lacked merit and was dismissed with costs.

Court Disposition

application dismissed with costs

Orders

  • The 3rd defendant's application dated 20/05/2022 is dismissed with costs.
  • The matter will be mentioned on 20/6/2023 for issuance of a hearing date.