[2024] KEHC 5364 (KLR)

[2024] KEHC 5364 (KLR)

The High Court found that while there was a contractual relationship between the parties for waterproofing works, the evidence did not support the respondent's claim for Kshs. 299,264/=. The court established, based on the documents and admissions, that the appellant had paid Kshs. 231,752/= to the respondent. The...

Source-derived case information.

Citation
[2024] KEHC 5364 (KLR)
Parties
Appellant: Kartar Singh Dhupar & Co. Limited; Respondent: Mau West & Co. Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Appeal E124 of 2020
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal_allowed_in_part
Judges
HI Ong'udi
Legal Topics
Contractual Disputes, Proof of Payment, Burden of Proof, Quantification of Claims
Source Language
en
Commercial and Corporate Civil Procedure Contractual Disputes Proof of Payment Burden of Proof Quantification of Claims

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kartar Singh Dhupar & Co. Limited

Appellant

Mau West & Co. Limited

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the respondent proved its claim for the principal sum of Kshs. 299,264/=.
  2. 2 Whether the trial magistrate erred in awarding the respondent the sum of Kshs. 299,264/=.
  3. 3 Whether the appellant had paid the amounts claimed or any part thereof to the respondent.

Ratio Decidendi

The High Court found that while there was a contractual relationship between the parties for waterproofing works, the evidence did not support the respondent's claim for Kshs. 299,264/=. The court established, based on the documents and admissions, that the appellant had paid Kshs. 231,752/= to the respondent. The respondent failed to justify or prove the claimed amount of Kshs. 299,264/=. The court recalculated the sums due for the services rendered (Kshs. 119,364/=, Kshs. 196,620/=, and Kshs. 41,760/=, totaling Kshs. 357,744/=), deducted the amount paid (Kshs. 231,752/=), and determined that the correct balance due was Kshs. 125,992/=. The trial court's judgment was set aside and...

Court Disposition

appeal_allowed_in_part

Orders

  • The trial court’s judgment is set aside and substituted with judgment for Kshs. 125,992/= in favour of the respondent.