[2019] KECA 866 (KLR)

[2019] KECA 866 (KLR)

The Court of Appeal held that while the appellant had locus standi to sue as a third-party beneficiary to the performance bond, the evidence did not establish that the respondent bank's delayed payment of the bond caused the detention of the appellant's equipment. The court found that the detention was a direct...

Source-derived case information.

Citation
[2019] KECA 866 (KLR)
Parties
Appellant: Karuri Civil Engineering (K) Limited; Respondent: Equity Bank Limited
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 339 of 2012
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed; trial court's dismissal of claim and counterclaim affirmed; each party to bear own costs
Judges
F Sichale
Legal Topics
Performance Bonds, Privity of Contract, Special Damages, Remoteness of Damage, Third Party Beneficiaries
Source Language
en
Commercial and Corporate Civil Procedure Performance Bonds Privity of Contract Special Damages Remoteness of Damage Third Party Beneficiaries

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 15 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Karuri Civil Engineering (K) Limited

Appellant

Equity Bank Limited

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the respondent bank was liable to the appellant for loss of user of detained equipment due to delayed payment under a performance bond.
  2. 2 Whether the doctrine of privity of contract barred the appellant from suing on the performance bond as a third-party beneficiary.
  3. 3 Whether the trial court erred in finding that the performance bond and advance payment bond were separate and distinct for purposes of liability.

Ratio Decidendi

The Court of Appeal held that while the appellant had locus standi to sue as a third-party beneficiary to the performance bond, the evidence did not establish that the respondent bank's delayed payment of the bond caused the detention of the appellant's equipment. The court found that the detention was a direct result of the appellant's own non-performance of the underlying contract with the Department of Defence, not the delay in payment by the bank. The performance bond did not reference the appellant's equipment, and any loss suffered was not attributable to the respondent. The court further held that the trial judge's approach was not contradictory, as it properly distinguished...

Court Disposition

appeal dismissed; trial court's dismissal of claim and counterclaim affirmed; each party to bear own costs

Orders

  • The appeal is dismissed.
  • The trial court's dismissal of the claim and counterclaim is affirmed.