[2021] KEHC 1462 (KLR)

[2021] KEHC 1462 (KLR)

The court found that the plaintiff had established ownership of Plot No.275 through documentary evidence, including a share certificate, beacon certificate, and a letter from the 2nd defendant confirming his ownership. The 1st defendant, despite having filed a defence, failed to attend the hearing or challenge the...

Source-derived case information.

Citation
[2021] KEHC 1462 (KLR)
Parties
Plaintiff: Kenneth Kang’ethe Chege; Defendant: Alexander Kisilu; Defendant: Embakasi /Njiru United Self Help Group through Meshack Ambuka; Defendant: Bernard Maina
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Environment & Land Case 440 of 2012
Procedural Posture
Land and Property Suit / Judgment
Outcome
Plaintiff’s claim allowed in part; permanent injunction, declaration of ownership, transfer order, removal of structures, general damages for trespass, and costs awarded. Claim for compensation for developments on Plot No.274 dismissed.
Legal Topics
Trespass to Land, Ownership Disputes, Injunctive Relief, Title Confirmation
Source Language
en
Land and Property Trespass to Land Ownership Disputes Injunctive Relief Title Confirmation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kenneth Kang’ethe Chege

Plaintiff

Alexander Kisilu

Defendant

Embakasi /Njiru United Self Help Group through Meshack Ambuka

Defendant

Bernard Maina

Defendant

Procedural Posture

Land and Property Suit / Judgment

  1. 1 Whether the plaintiff is the lawful owner of Plot No.275 within Embakasi/Njiru United Self Help Group Komarock Phase III Project Nairobi.
  2. 2 Whether the 1st defendant trespassed on the plaintiff’s property.
  3. 3 Whether the plaintiff is entitled to injunctive relief and damages for trespass.

Ratio Decidendi

The court found that the plaintiff had established ownership of Plot No.275 through documentary evidence, including a share certificate, beacon certificate, and a letter from the 2nd defendant confirming his ownership. The 1st defendant, despite having filed a defence, failed to attend the hearing or challenge the plaintiff’s evidence. The court determined that the 1st defendant had erroneously constructed on the plaintiff’s plot, constituting trespass. The plaintiff’s claim for compensation for developments on Plot No.274 was dismissed due to lack of evidence. The court granted the plaintiff’s prayers for injunctive relief, a declaration of ownership, transfer of the plot, removal of the...

Court Disposition

Plaintiff’s claim allowed in part; permanent injunction, declaration of ownership, transfer order, removal of structures, general damages for trespass, and costs awarded. Claim for compensation for developments on Plot No.274 dismissed.

Orders

  • A permanent injunction restraining the 1st defendant from trespassing on, developing or otherwise dealing with Plot No.275 within the Scheme of Embakasi/Njiru United Self Help Group Komarock Phase III Project Nairobi.
  • A permanent injunction restraining the Embakasi/Njiru United Self Help Group through the 2nd and 3rd defendants or any other officials from selling, disposing of, alienating, transferring or otherwise interfering with Plot No.275.