The court found that the plaintiff had already participated in a consent process that allowed for separate valuations by each party's chosen valuer, and the plaintiff had not provided any explanation for failing to engage the National Land Commission at that stage. The court emphasized that it is the responsibility...

Source-derived case information.

Citation
[2024] KEELC 6915 (KLR)
Parties
Plaintiff: Kenya Electricity and Transmission Company Limited; Defendant: Mahmood Kassam & 4 others
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case 208 of 2021
Procedural Posture
Environment and Land Case / Ruling on Interlocutory Application
Outcome
Application dismissed with costs to the defendants.
Judges
SM Kibunja
Legal Topics
Wayleave Valuation, Consent Orders, Interlocutory Applications, Costs Award
Source Language
en
Land and Property Civil Procedure Wayleave Valuation Consent Orders Interlocutory Applications Costs Award

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Kenya Electricity and Transmission Company Limited

Plaintiff

Mahmood Kassam & 4 others

Defendant

Procedural Posture

Environment and Land Case / Ruling on Interlocutory Application

  1. 1 Whether the plaintiff has established a reasonable case for a further wayleave valuation by the National Land Commission before trial.
  2. 2 Who should bear the costs of the application.

Ratio Decidendi

The court found that the plaintiff had already participated in a consent process that allowed for separate valuations by each party's chosen valuer, and the plaintiff had not provided any explanation for failing to engage the National Land Commission at that stage. The court emphasized that it is the responsibility of each party to gather and file all necessary evidence at the appropriate time in the proceedings. Since the plaintiff's expert had already conducted a valuation and filed the report, there was no basis for a further valuation by the National Land Commission. The application was therefore without merit, and the court saw no reason to depart from the principle that costs follow...

Court Disposition

Application dismissed with costs to the defendants.

Orders

  • The plaintiff's notice of motion dated 2nd May 2024 is dismissed.