[2025] KEELC 4468 (KLR)

[2025] KEELC 4468 (KLR)

The court found no evidence of any consent or error on the face of the record to justify review, variation, or setting aside of the interim orders granted on 14.01.2025. The extracted order accurately reflected the court's decision, and the defendant's remedy, if dissatisfied, lay in appeal rather than review. On...

Source-derived case information.

Citation
[2025] KEELC 4468 (KLR)
Parties
Plaintiff: Kenya Electricity Transmission Co Ltd (K); Defendant: Hacienda Development Ltd; Interested Party: Kenya Power & Lighting Co Ltd
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Enviromental and Land Originating Summons E024 of 2024
Procedural Posture
Environment and Land Originating Summons / Ruling on Interlocutory Applications (injunction and Review)
Outcome
Plaintiff's application for interim injunction allowed; defendant's application for review dismissed.
Judges
YM Angima
Legal Topics
Wayleave Rights, Interim Injunctions, Review of Court Orders, Compulsory Acquisition, Compensation for Land, Construction Projects
Source Language
en
Land and Property Civil Procedure Wayleave Rights Interim Injunctions Review of Court Orders Compulsory Acquisition Compensation for Land Construction Projects

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kenya Electricity Transmission Co Ltd (K)

Plaintiff

Hacienda Development Ltd

Defendant

Kenya Power & Lighting Co Ltd

Interested Party

Procedural Posture

Environment and Land Originating Summons / Ruling on Interlocutory Applications (injunction and Review)

  1. 1 Whether the defendant has established grounds for review, variation or setting aside of the interim orders made on 14.01.2025.
  2. 2 Whether the plaintiff has made out a case for the grant of an interim injunction restraining interference with the electricity transmission project.
  3. 3 Who should bear the costs of the two applications.

Ratio Decidendi

The court found no evidence of any consent or error on the face of the record to justify review, variation, or setting aside of the interim orders granted on 14.01.2025. The extracted order accurately reflected the court's decision, and the defendant's remedy, if dissatisfied, lay in appeal rather than review. On the injunction, the court held that the plaintiff had demonstrated a prima facie case through credible evidence of a wayleave and written permission from KPLC. The risk of irreparable loss was established, as monetary compensation would not suffice for loss of public utilities. The court therefore granted the interim injunction as sought. Costs were awarded in line with the...

Court Disposition

Plaintiff's application for interim injunction allowed; defendant's application for review dismissed.

Orders

  • The defendant's notice of motion dated 31.01.2025 is dismissed with costs.
  • The plaintiff's notice of motion dated 18.12.2024 is allowed in terms of orders Nos. 3 and 4 thereof with costs in the cause.