The court found that the plaintiff specifically requested a bid bond valid for 120 days from the tender closing date, and the defendant, despite being a professional banking institution, issued a bond valid for only 119 days. This failure constituted a clear breach of contract. The evidence established that the...

Source-derived case information.

Citation
[2021] KEHC 8834 (KLR)
Parties
Plaintiff: Kenya Haulage Agency Limited; Defendant: Stanbic Bank (K) Limited
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 180 of 2021
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff
Judges
CA Otieno
Legal Topics
Breach of Contract, Bank Guarantees, Damages for Loss of Opportunity, Public Procurement, Remoteness of Damages
Source Language
en
Commercial and Corporate Banking and Finance Breach of Contract Bank Guarantees Damages for Loss of Opportunity Public Procurement Remoteness of Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 13 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Kenya Haulage Agency Limited

Plaintiff

Stanbic Bank (K) Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Was the defendant in breach of contract by issuing a bid bond with a validity period less than requested by the plaintiff?
  2. 2 Did the breach by the defendant cause the plaintiff to lose the tender opportunity?
  3. 3 Is the plaintiff entitled to damages for loss of profit as claimed?

Ratio Decidendi

The court found that the plaintiff specifically requested a bid bond valid for 120 days from the tender closing date, and the defendant, despite being a professional banking institution, issued a bond valid for only 119 days. This failure constituted a clear breach of contract. The evidence established that the procuring entity rejected the plaintiff's tender solely due to the insufficient validity period of the bid bond. The court held that the loss of opportunity to win the tender and the associated profit was a foreseeable consequence of the defendant's breach, and such loss was not too remote. The court accepted the plaintiff's calculation of the lost profit as the difference between...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered for the plaintiff against the defendant in the sum of USD 250,860.
  • Interest at court rates from the date of suit until payment in full.