[2023] KEHC 18383 (KLR)

[2023] KEHC 18383 (KLR)

The Plaintiff failed to complete the contract works by the stipulated completion date, having only completed 90% and not delivered the Bed Head units as required. The contract expressly required completion by 22nd February 2016, and the Plaintiff's own admission confirmed non-compliance. The court found that the...

Source-derived case information.

Citation
[2023] KEHC 18383 (KLR)
Parties
Plaintiff: Kenya Medical Engineering Limited; Defendant: Board of Trustee of Catherine Mcauley Nursing School & Mater Misericordiae Hospital; Defendant: Shapa Consulting Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Case 62 of 2016
Procedural Posture
Commercial Case / Judgment
Outcome
Plaintiff's suit dismissed with costs to the 1st Defendant.
Judges
DAS Majanja
Legal Topics
Breach of Contract, Construction Contracts, Damages for Breach, Pleading and Proof of Special Damages
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Damages for Breach Pleading and Proof of Special Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 11 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Kenya Medical Engineering Limited

Plaintiff

Board of Trustee of Catherine Mcauley Nursing School & Mater Misericordiae Hospital

Defendant

Shapa Consulting Limited

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Whether the 1st Defendant breached the contract with the Plaintiff by terminating it before completion date.
  2. 2 Whether the Plaintiff is entitled to damages for alleged breach of contract.

Ratio Decidendi

The Plaintiff failed to complete the contract works by the stipulated completion date, having only completed 90% and not delivered the Bed Head units as required. The contract expressly required completion by 22nd February 2016, and the Plaintiff's own admission confirmed non-compliance. The court found that the Defendant did not breach the contract by terminating it, as the contract had lapsed by its own terms. Even if breach were established, the Plaintiff failed to prove entitlement to damages: the certified sum claimed had already been paid (less withholding tax), and no special damages were pleaded or proved as required by law. General and aggravated damages are not recoverable for...

Court Disposition

Plaintiff's suit dismissed with costs to the 1st Defendant.

Orders

  • The Plaintiff's suit is dismissed.
  • The Plaintiff shall pay costs to the 1st Defendant.