[2015] KEHC 3243 (KLR)

[2015] KEHC 3243 (KLR)

The court found that there was no contract between the applicant (Kenya National Highways Authority) and the 1st respondent (Masosa Construction Limited), as the agreement in question was signed by SBI International AG Kenya and Masosa Construction Limited, with SBI purporting to sign on behalf of the applicant...

Source-derived case information.

Citation
[2015] KEHC 3243 (KLR)
Parties
Applicant: Kenya National Highways Authority; Respondent: Masosa Construction Limited; Respondent: QS Newton Dishon Maungu (Sole Arbitrator)
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Suit 565 of 2014
Procedural Posture
Miscellaneous Application / Ruling on Application to Set Aside Arbitral Tribunal's Preliminary Ruling
Outcome
Originating summons successful; arbitral tribunal's preliminary ruling set aside; declaration that tribunal lacked jurisdiction; costs to applicant.
Legal Topics
Arbitration Agreement, Jurisdiction of Arbitral Tribunal, Privity of Contract, Contractual Relationship, Incorporation of Terms
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Agreement Jurisdiction of Arbitral Tribunal Privity of Contract Contractual Relationship Incorporation of Terms

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Kenya National Highways Authority

Applicant

Masosa Construction Limited

Respondent

QS Newton Dishon Maungu (Sole Arbitrator)

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application to Set Aside Arbitral Tribunal's Preliminary Ruling

  1. 1 Whether there existed a contract between the applicant and the 1st respondent.
  2. 2 Whether there was an arbitration agreement binding the applicant and the 1st respondent.
  3. 3 Whether the arbitral tribunal had jurisdiction to determine the dispute between the applicant and the 1st respondent.

Ratio Decidendi

The court found that there was no contract between the applicant (Kenya National Highways Authority) and the 1st respondent (Masosa Construction Limited), as the agreement in question was signed by SBI International AG Kenya and Masosa Construction Limited, with SBI purporting to sign on behalf of the applicant without its authority. The court held that the applicant could not be bound by an arbitration agreement incorporated into a contract to which it was not a party and had not authorized or ratified. The court further held that the arbitral tribunal exceeded its mandate by making final determinations on substantive issues before establishing its jurisdiction. Consequently, the...

Court Disposition

Originating summons successful; arbitral tribunal's preliminary ruling set aside; declaration that tribunal lacked jurisdiction; costs to applicant.

Orders

  • The preliminary ruling of the arbitral tribunal is set aside.
  • It is declared that the arbitral tribunal lacked jurisdiction to hear and determine the dispute between the applicant and the 1st respondent.