[2011] KECA 308 (KLR)

[2011] KECA 308 (KLR)

The Court found that the intended appeal was arguable, particularly regarding the scope of the easement and whether it permitted the laying of an additional pipeline. On the balance of convenience, the Court held that the public interest in the multi-billion pipeline project outweighed the respondent's individual...

Source-derived case information.

Citation
[2011] KECA 308 (KLR)
Parties
Applicant: Kenya Pipeline Company Limited; Respondent: Stanley Munga Githunguri
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Application 300 of 2010
Procedural Posture
Stay Application / Application for Stay of Execution Pending Appeal
Outcome
Application for stay of execution granted.
Judges
J Wakiaga, ARM Visram, JW Nyamu
Legal Topics
Easements, Injunctions, Public Interest, Proportionality, Trespass, Compensation for Land
Source Language
en
Land and Property Civil Procedure Easements Injunctions Public Interest Proportionality Trespass Compensation for Land

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kenya Pipeline Company Limited

Applicant

Stanley Munga Githunguri

Respondent

Procedural Posture

Stay Application / Application for Stay of Execution Pending Appeal

  1. 1 Whether the registered easement permits the applicant to lay an additional pipeline on the respondent's land.
  2. 2 Whether the High Court was correct in granting an injunction restraining the applicant from laying a new pipeline.
  3. 3 Whether the balance of convenience and public interest favour granting a stay of execution of the High Court's order.

Ratio Decidendi

The Court found that the intended appeal was arguable, particularly regarding the scope of the easement and whether it permitted the laying of an additional pipeline. On the balance of convenience, the Court held that the public interest in the multi-billion pipeline project outweighed the respondent's individual claim, especially since the respondent could be compensated in damages if successful. The Court applied the principle of proportionality, noting that the harm to the applicant and the public from delaying the project would be far greater than any harm to the respondent. Accordingly, the Court granted a stay of the High Court's injunctive order (order 4), pending the hearing and...

Court Disposition

Application for stay of execution granted.

Orders

  • Order 4 of the High Court orders dated 16th December 2010 is stayed pending the hearing and determination of the intended appeal.
  • Costs of this application to be in the appeal.