[1997] KEHC 22 (KLR)

[1997] KEHC 22 (KLR)

The court found that the defendants breached the construction contract by failing to complete the housing project within the agreed period and by failing to provide the agreed loan of Kshs. 10 million. Despite the plaintiff making all required payments, the project was not completed, and the plaintiff had to engage...

Source-derived case information.

Citation
[1997] KEHC 22 (KLR)
Parties
Plaintiff: Kenya Police Staff Savings and Credit Co-operative Society Ltd; Defendant: Kensing International Ltd; Defendant: Kensing Consulting Engineers Company Ltd; Defendant: Kensing and Partners Consulting Engineers Ltd; Defendant: Benjamin Ndubai and Chloris Ndubai and Kensing and Partners Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 2560 of 1988
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff
Legal Topics
Breach of Contract, Construction Disputes, Damages Assessment, Joint and Several Liability
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Disputes Damages Assessment Joint and Several Liability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Kenya Police Staff Savings and Credit Co-operative Society Ltd

Plaintiff

Kensing International Ltd

Defendant

Kensing Consulting Engineers Company Ltd

Defendant

Kensing and Partners Consulting Engineers Ltd

Defendant

Benjamin Ndubai and Chloris Ndubai and Kensing and Partners Ltd

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendants breached the construction contract by failing to complete the housing project within the agreed period.
  2. 2 Whether the defendants failed to provide the agreed loan of Kshs. 10 million to the plaintiff.
  3. 3 Whether the plaintiff is entitled to damages for losses incurred due to the defendants' breaches.

Ratio Decidendi

The court found that the defendants breached the construction contract by failing to complete the housing project within the agreed period and by failing to provide the agreed loan of Kshs. 10 million. Despite the plaintiff making all required payments, the project was not completed, and the plaintiff had to engage another contractor at a significantly higher cost. The court determined that the breach that counted was the failure to complete the project after the revised agreement of 13th February, 1987, which had addressed prior issues. As a result of the defendants' breach, the plaintiff incurred a loss of Kshs. 16 million, representing the difference between the final cost and the...

Court Disposition

judgment for the plaintiff

Orders

  • Defendants jointly and severally to pay the plaintiff Kshs. 16 million as special damages for loss suffered.
  • Defendants jointly and severally to pay the plaintiff Kshs. 1,000,000 as general damages for breach of contract.