[2020] KEHC 643 (KLR)

[2020] KEHC 643 (KLR)

The court found that the respondent failed to prove that the appellant's conduct was oppressive or vindictive to justify an award of general damages for breach of contract. The respondent did not provide sufficient evidence of payment of bills or of the alleged overpayment and business losses. The appellant was...

Source-derived case information.

Citation
[2020] KEHC 643 (KLR)
Parties
Appellant: Kenya Power & Lighting Co. Ltd; Respondent: Nelson Osiebe
Court
High Court
Court Station
High Court at Kisii
Jurisdiction
Kenya
Case Number
Civil Appeal 17 of 2019
Procedural Posture
Civil Appeal / Judgment on First Appeal
Outcome
Appeal allowed in part; subordinate court's judgment set aside in substantial respects; cross-appeal struck out; each party to bear own costs.
Judges
REA Ougo
Legal Topics
Breach of Contract, Electricity Supply Disputes, Damages Quantification, Special and General Damages, Contractual Obligations, Appeals Procedure
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Electricity Supply Disputes Damages Quantification Special and General Damages Contractual Obligations Appeals Procedure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 17 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Kenya Power & Lighting Co. Ltd

Appellant

Nelson Osiebe

Respondent

Procedural Posture

Civil Appeal / Judgment on First Appeal

  1. 1 Whether the appellant was liable for breach of contract in the supply of electricity to the respondent.
  2. 2 Whether the respondent was entitled to general and/or special damages for alleged loss of business and overpayment.
  3. 3 Whether the appellant was justified in disconnecting electricity supply for non-payment.

Ratio Decidendi

The court found that the respondent failed to prove that the appellant's conduct was oppressive or vindictive to justify an award of general damages for breach of contract. The respondent did not provide sufficient evidence of payment of bills or of the alleged overpayment and business losses. The appellant was justified in disconnecting the electricity supply due to non-payment, as permitted by law. The trial court's award of general damages and certain declaratory and injunctive orders was set aside. The court apportioned liability for the disputed bill of Kshs 134,741 equally between the parties, reflecting both the appellant's delay in addressing the faulty meter and the respondent's...

Court Disposition

Appeal allowed in part; subordinate court's judgment set aside in substantial respects; cross-appeal struck out; each party to bear own costs.

Orders

  • Subordinate court's orders (b), (c), (d), (e), (f), and (g) set aside.
  • The bill amounting to Kshs 134,741 to be shared equally between appellant and respondent (50:50).