[2023] KECA 514 (KLR)

[2023] KECA 514 (KLR)

The court found that the respondent failed to include a certificate of delay in the original record of appeal, which is a mandatory requirement to exclude the period taken to obtain proceedings from the computation of time. The subsequent introduction of the certificate of delay via a supplementary record was deemed...

Source-derived case information.

Citation
[2023] KECA 514 (KLR)
Parties
Applicant: Kenya Revenue Authority; Respondent: Tom Odhiambo Ojienda t/a Prof Tom Ojienda & Associates
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal (Application) 285 of 2018
Procedural Posture
Civil Appeal / Ruling on Applications to Strike Out Record of Appeal and for Extension of Time
Outcome
appeal struck out as filed out of time; each party to bear its own costs
Judges
A Ali-Aroni, JM Mativo, PM Gachoka
Legal Topics
Appeal Timelines, Certificate of Delay, Extension of Time, Striking Out Appeal
Source Language
en
Civil Procedure Appeal Timelines Certificate of Delay Extension of Time Striking Out Appeal

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Kenya Revenue Authority

Applicant

Tom Odhiambo Ojienda t/a Prof Tom Ojienda & Associates

Respondent

Procedural Posture

Civil Appeal / Ruling on Applications to Strike Out Record of Appeal and for Extension of Time

  1. 1 Whether the appeal was filed within the prescribed time under the Court of Appeal Rules.
  2. 2 Whether the absence of a certificate of delay in the original record of appeal invalidates the appeal.
  3. 3 Whether the application for extension of time should be entertained given the settlement of the dispute.

Ratio Decidendi

The court found that the respondent failed to include a certificate of delay in the original record of appeal, which is a mandatory requirement to exclude the period taken to obtain proceedings from the computation of time. The subsequent introduction of the certificate of delay via a supplementary record was deemed a late and ineffective attempt to cure the defect. As a result, the appeal was lodged 30 days out of time and was not properly before the court. Furthermore, the parties had settled the underlying dispute, rendering the application for extension of time moot. The court therefore struck out the appeal and ordered each party to bear its own costs.

Court Disposition

appeal struck out as filed out of time; each party to bear its own costs

Orders

  • The appeal dated August 15, 2018 is hereby struck out.
  • Each party shall bear its own costs.