[2021] KEELRC 2116 (KLR)

[2021] KEELRC 2116 (KLR)

The court found that the omission of final orders on general wage increase and the duration and effective date of the CBA in its earlier judgment warranted review for clarity and completeness. The court rejected the respondent's proposal to condition wage increments on revenue thresholds, instead adopting the...

Source-derived case information.

Citation
[2021] KEELRC 2116 (KLR)
Parties
Applicant: Kenya Union of Commercial Food & Allied Workers; Respondent: Kahuti Water & Sanitation Co. Limited
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Nyeri
Jurisdiction
Kenya
Case Number
Cause 34 of 2019
Procedural Posture
Review Application / Ruling on Application to Review Judgment for Clarification and Final Orders
Outcome
Application allowed; judgment reviewed to include final orders on wage increase, duration, and effective date of CBA.
Judges
DKN Marete
Legal Topics
Collective Bargaining Agreements, Wage Increments, Duration of Cba, Effective Date of Cba
Source Language
en
Employment and Labour Collective Bargaining Agreements Wage Increments Duration of Cba Effective Date of Cba

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Kenya Union of Commercial Food & Allied Workers

Applicant

Kahuti Water & Sanitation Co. Limited

Respondent

Procedural Posture

Review Application / Ruling on Application to Review Judgment for Clarification and Final Orders

  1. 1 Whether the court should review its judgment to include final orders on general wage increase and the duration and effective date of the collective bargaining agreement.
  2. 2 Whether the general wage increase should be pegged to the respondent's revenue performance or determined by the Consumer Price Index as recommended by the Central Planning and Monitoring Unit.
  3. 3 What should be the duration and effective date of the collective bargaining agreement.

Ratio Decidendi

The court found that the omission of final orders on general wage increase and the duration and effective date of the CBA in its earlier judgment warranted review for clarity and completeness. The court rejected the respondent's proposal to condition wage increments on revenue thresholds, instead adopting the Central Planning and Monitoring Unit's analysis of a 13.2% CPI increase over two years, adjusted to 15.2% for fairness, and ordered a 10% increment in the first year and 5.2% in the second year for all employee cadres. The court set the CBA duration at two years, in line with established practice, and held that the effective date would be the date of registration of the CBA, as...

Court Disposition

Application allowed; judgment reviewed to include final orders on wage increase, duration, and effective date of CBA.

Orders

  • General wage increase pegged at 10% in the first year and 5.2% in the second year of the CBA for all cadres of employees.
  • Duration of the CBA set at two years.