[2009] KEHC 1718 (KLR)

[2009] KEHC 1718 (KLR)

The court found that while there was a dispute regarding the larger sum claimed by the plaintiff (Kshs.6,267,725.40), the defendant had unequivocally admitted liability for Kshs.2,500,000 in correspondence, with the only condition being payment by the Ministry of Roads and Public Works. The defendant did not assert...

Source-derived case information.

Citation
[2009] KEHC 1718 (KLR)
Parties
Plaintiff: Kewal Contractors Limited; Defendant: Coastal Enterprises Kenya Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 402 of 2006
Procedural Posture
Civil Suit / Ruling on Notice of Motion for Summary Judgment And/or Judgment on Admission
Outcome
Plaintiff's application succeeds in part; judgment entered for Kshs.2,500,000 on admission; remainder of claim to proceed to full trial.
Judges
AT Sitati
Legal Topics
Summary Judgment, Judgment on Admission, Breach of Contract, Sub Contract Disputes
Source Language
en
Commercial and Corporate Civil Procedure Summary Judgment Judgment on Admission Breach of Contract Sub Contract Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kewal Contractors Limited

Plaintiff

Coastal Enterprises Kenya Ltd

Defendant

Procedural Posture

Civil Suit / Ruling on Notice of Motion for Summary Judgment And/or Judgment on Admission

  1. 1 Whether the plaintiff is entitled to summary judgment for Kshs.6,267,725.40 as part of its claim for work done under the sub-contract.
  2. 2 Whether judgment on admission should be entered for the plaintiff for Kshs.2,500,000 based on the defendant's correspondence and admissions.
  3. 3 Whether the defendant's defence raises triable issues that warrant a full hearing.

Ratio Decidendi

The court found that while there was a dispute regarding the larger sum claimed by the plaintiff (Kshs.6,267,725.40), the defendant had unequivocally admitted liability for Kshs.2,500,000 in correspondence, with the only condition being payment by the Ministry of Roads and Public Works. The defendant did not assert that such payment had not been made. The court held that this admission was clear and binding, and that the defendant's defence did not specifically address or deny this admitted amount. Accordingly, judgment on admission was appropriate for Kshs.2,500,000. The remaining claims, involving disputed facts and issues such as VAT and alleged repair costs, were deemed to raise...

Court Disposition

Plaintiff's application succeeds in part; judgment entered for Kshs.2,500,000 on admission; remainder of claim to proceed to full trial.

Orders

  • Judgment is entered for the plaintiff in the sum of Kshs.2,500,000 as part of the claim.
  • Plaintiff is awarded costs and interest at court rates on the sum of Kshs.2,500,000.