[2018] KEHC 1253 (KLR)

[2018] KEHC 1253 (KLR)

The court found that the plaintiff was in breach of contract by refusing to allow the defendant to complete the repair works after his acquittal, despite there being no evidence of delay or neglect by the defendant. The contract's termination clause required proof of delay or neglect, which was not established. The...

Source-derived case information.

Citation
[2018] KEHC 1253 (KLR)
Parties
Plaintiff: Kibugi Farmers Co-op Society; Defendant: Philip Mungai t/a Mungai Electrical Ventures
Court
High Court
Court Station
High Court at Embu
Jurisdiction
Kenya
Case Number
Civil Case 61 of 1996
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiff's suit dismissed; defendant's counterclaim partly succeeds.
Judges
FN Muchemi
Legal Topics
Breach of Contract, Contractual Obligations, Termination of Contract, Damages for Breach, Costs Award
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Contractual Obligations Termination of Contract Damages for Breach Costs Award

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kibugi Farmers Co-op Society

Plaintiff

Philip Mungai t/a Mungai Electrical Ventures

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff or defendant was in breach of the contract.
  2. 2 What remedies are available to the party affected by the breach.
  3. 3 Whether the defendant is entitled to damages for loss of business.

Ratio Decidendi

The court found that the plaintiff was in breach of contract by refusing to allow the defendant to complete the repair works after his acquittal, despite there being no evidence of delay or neglect by the defendant. The contract's termination clause required proof of delay or neglect, which was not established. The plaintiff's unilateral termination and refusal to permit the defendant to finish the works constituted a fundamental breach. The defendant's claim for loss of business was not proved, as there was no evidence linking the plaintiff to the loss caused by the District Agricultural Officer's letter. The defendant was entitled to the balance of the contract sum for phase 3, but not...

Court Disposition

Plaintiff's suit dismissed; defendant's counterclaim partly succeeds.

Orders

  • Plaintiff's claim is dismissed.
  • Defendant is awarded Kshs. 189,992 as damages for breach of contract, being the balance of the contract fee, with interest at court rates from the date of filing the counterclaim.