[2016] KEHC 1375 (KLR)

[2016] KEHC 1375 (KLR)

The court found that the defendant issued Local Purchase Orders to the plaintiff for the installation of Base Transceiver Stations at various sites, and the plaintiff performed the work as specified. The evidence, including LPOs, emails, and payment records, established that there was a contractual relationship and...

Source-derived case information.

Citation
[2016] KEHC 1375 (KLR)
Parties
Plaintiff: Kilele Builders Limited; Defendant: TKM Maestro
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 290 of 2012
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff
Legal Topics
Contractual Debt Recovery, Local Purchase Orders, Performance of Contract, Quantum of Claim, Interest on Debt
Source Language
en
Commercial and Corporate Contractual Debt Recovery Local Purchase Orders Performance of Contract Quantum of Claim Interest on Debt

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kilele Builders Limited

Plaintiff

TKM Maestro

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendant contracted the plaintiff to install Base Transceiver Stations at various sites in Kenya.
  2. 2 Whether the plaintiff performed the contractual obligations as per the Local Purchase Orders issued by the defendant.
  3. 3 Whether the defendant is indebted to the plaintiff for the claimed sum and liable to pay interest and costs.

Ratio Decidendi

The court found that the defendant issued Local Purchase Orders to the plaintiff for the installation of Base Transceiver Stations at various sites, and the plaintiff performed the work as specified. The evidence, including LPOs, emails, and payment records, established that there was a contractual relationship and that the plaintiff fulfilled its obligations. The defendant's denials were undermined by its own correspondence acknowledging the debt and discussing payment arrangements. The court held that the plaintiff had proved its claim on a balance of probabilities and was entitled to the outstanding sum, interest at court rates from the date of filing, and costs. The absence of a...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered in favour of the plaintiff for Kshs. 5,266,500.76.
  • Interest awarded at court rates from 8th May 2012 until payment in full.