[2013] KECA 354 (KLR)

[2013] KECA 354 (KLR)

The Court of Appeal held that the contract was not frustrated by the nationwide power rationing because the respondent offered reasonable and practical alternatives to maintain performance, including providing alternative power sources at her own expense. The appellant's refusal to accept these alternatives and its...

Source-derived case information.

Citation
[2013] KECA 354 (KLR)
Parties
Appellant: Kilimani Junior Academy Ltd; Respondent: Mildred Machanga T/A Learn It
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 166 of 2005
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed
Legal Topics
Breach of Contract, Liquidated Damages, Frustration of Contract, Force Majeure, Termination of Contract
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Liquidated Damages Frustration of Contract Force Majeure Termination of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kilimani Junior Academy Ltd

Appellant

Mildred Machanga T/A Learn It

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the contract between the appellant and respondent was frustrated by the nationwide power rationing.
  2. 2 Whether the respondent was entitled to liquidated damages following the appellant's repudiation of the contract.
  3. 3 Whether the availability of electric power was a fundamental or implied term of the contract.

Ratio Decidendi

The Court of Appeal held that the contract was not frustrated by the nationwide power rationing because the respondent offered reasonable and practical alternatives to maintain performance, including providing alternative power sources at her own expense. The appellant's refusal to accept these alternatives and its insistence on terminating the contract amounted to a repudiation. The court found that the contract did not make the availability of electric power from the national grid a fundamental or implied term, nor did it restrict the source of power. The absence of a force majeure clause precluded the appellant from relying on that defence. The respondent was therefore entitled to...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the respondent.
  • The judgment and decree of the High Court awarding Kshs. 3 million to the respondent is upheld.