[1985] KEHC 108 (KLR)

[1985] KEHC 108 (KLR)

The court found that the defendant failed to comply with the strict notice requirements under Clauses 4.44 and 4.45 of the General Conditions of Contract. The letters relied upon by the defendant as notices were either not issued by the proper party (the defendant itself) or did not signify that they were notices...

Source-derived case information.

Citation
[1985] KEHC 108 (KLR)
Parties
Plaintiff: Kilimanjaro Construction; Defendant: The East African Power & Lighting
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 846 of 1982
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff in part; counterclaim dismissed.
Legal Topics
Construction Contracts, Termination of Contracts, Damages for Breach, Performance Bonds
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Termination of Contracts Damages for Breach Performance Bonds

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kilimanjaro Construction

Plaintiff

The East African Power & Lighting

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendant lawfully terminated the construction contract under Clause 4.44 or 4.45 of the General Conditions of Contract.
  2. 2 Whether the plaintiff is entitled to damages for unlawful determination of the contract.
  3. 3 Whether the defendant is entitled to its counterclaim for losses incurred due to the plaintiff's alleged default.

Ratio Decidendi

The court found that the defendant failed to comply with the strict notice requirements under Clauses 4.44 and 4.45 of the General Conditions of Contract. The letters relied upon by the defendant as notices were either not issued by the proper party (the defendant itself) or did not signify that they were notices under the relevant clauses, and thus did not constitute valid notices for termination or cancellation. The court held that, given the size and nature of the contract, strict compliance with termination provisions was essential due to the grave financial consequences of premature determination. As a result, the contract was unlawfully determined by the defendant. The plaintiff was...

Court Disposition

Judgment for the plaintiff in part; counterclaim dismissed.

Orders

  • Judgment for the plaintiff for Kshs 458,229.91 as per final account and for amounts approved by Acres in Extra Work Certificate No 3.
  • Defendant's counterclaim for Kshs 11,486,427.97 is disallowed.