[2023] KEHC 17701 (KLR)

[2023] KEHC 17701 (KLR)

The court found that the plaintiff had legal capacity, as the defendant's search related to a different entity. A valid contract existed, evidenced by the tender process, notification of award, and execution of the contract. The defendant's reliance on section 63 of the Public Procurement and Asset Disposal Act was...

Source-derived case information.

Citation
[2023] KEHC 17701 (KLR)
Parties
Appellant: King Investment Management Ltd; Respondent: Rivatex East Africa Limited
Court
High Court
Court Station
High Court at Eldoret
Jurisdiction
Kenya
Case Number
Civil Appeal 17 of 2020
Procedural Posture
Civil Appeal / Judgment
Outcome
Judgment for the plaintiff; contract cancellation declared unlawful; specific performance granted; costs to plaintiff.
Judges
RN Nyakundi
Legal Topics
Public Procurement, Breach of Contract, Specific Performance, Force Majeure, Contractual Capacity, Tender Cancellation
Source Language
en
Commercial and Corporate Civil Procedure Public Procurement Breach of Contract Specific Performance Force Majeure Contractual Capacity Tender Cancellation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

King Investment Management Ltd

Appellant

Rivatex East Africa Limited

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the plaintiff had the legal capacity to contract.
  2. 2 Whether there was a valid contract between the parties.
  3. 3 Whether there was breach of contract by the defendant.

Ratio Decidendi

The court found that the plaintiff had legal capacity, as the defendant's search related to a different entity. A valid contract existed, evidenced by the tender process, notification of award, and execution of the contract. The defendant's reliance on section 63 of the Public Procurement and Asset Disposal Act was misplaced, as that provision only applies before notification of award, not after contract execution. The contract did not contain a force majeure clause, and the defendant failed to prove that COVID-19 or high prices justified termination. The plaintiff was ready and willing to perform, but the defendant failed to facilitate the irrevocable letter of credit, which was a...

Court Disposition

Judgment for the plaintiff; contract cancellation declared unlawful; specific performance granted; costs to plaintiff.

Orders

  • The letter of cancellation dated 26/03/2020 cancelling the contract for supply and delivery of polyester and viscose fibres tender no. REAL/38/2019-2020 is declared unlawful, irregular, unprocedural and null and void ab initio.
  • An order for specific performance compelling the defendant to provide an irrevocable letter of credit to the plaintiff's bank as provided in clause 6 of the contract is issued.