The Petition failed because the Petitioner did not plead and prove with precision how Articles 10, 40 and 47 were violated, and on the evidence the power lines predated her ownership of the land. Since the Respondent’s infrastructure existed before the Petitioner acquired title and the Petitioner did not prove...

Source-derived case information.

Citation
[2026] KEELC 2533 (KLR)
Parties
Petitioner: Catherine Gathigia Kiruki; Respondent: Kenya Power & Lighting Company Plc
Court
Environment and Land Court
Jurisdiction
Kenya
Case Number
Environment and Land Petition E007 of 2025
Procedural Posture
Constitutional/environment and Land Petition / Judgment
Outcome
Petition dismissed with costs to the Respondent.
Judges
["MAO Odeny"]
Legal Topics
Right to Property, Fair Administrative Action, Wayleave/utility Infrastructure, Trespass, Constitutional Petition Threshold, Burden of Proof, Laches, Compensation for Land Use
Source Language
en
Constitutional Law Environment and Land Law Property Law Administrative Law Right to Property Fair Administrative Action Wayleave/utility Infrastructure Trespass +4 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 20 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Catherine Gathigia Kiruki

Petitioner

Kenya Power & Lighting Company Plc

Respondent

Procedural Posture

Constitutional/environment and Land Petition / Judgment

  1. 1 Whether the Petition met the constitutional pleading threshold in Anarita Karimi Njeru and Mumo Matemu
  2. 2 Whether the Respondent violated Articles 10, 40 and 47 of the Constitution
  3. 3 Whether the Respondent trespassed on or unlawfully occupied the Petitioner’s land

Ratio Decidendi

The Petition failed because the Petitioner did not plead and prove with precision how Articles 10, 40 and 47 were violated, and on the evidence the power lines predated her ownership of the land. Since the Respondent’s infrastructure existed before the Petitioner acquired title and the Petitioner did not prove unlawful entry, lack of lawful basis, or any actual constitutional injury, no trespass or constitutional infringement was established.

Court Disposition

Petition dismissed with costs to the Respondent.

Orders

  • The Petition is dismissed.
  • Costs are awarded to the Respondent.