[2017] KEHC 2521 (KLR)

[2017] KEHC 2521 (KLR)

The court found that the contract between the parties was clear, written, and did not contain any express terms regarding timelines or the Plaintiff’s capacity. The Defendant, having drafted the contract, could not seek to imply terms that were not included. Both parties contributed to delays in the project, and...

Source-derived case information.

Citation
[2017] KEHC 2521 (KLR)
Parties
Plaintiff: Kisumu Concrete Products Ltd; Defendant: Cementers Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 612 of 2012
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiff's claim allowed; Defendant's counterclaim dismissed.
Judges
GL Nzioka
Legal Topics
Breach of Contract, Quantum Meruit, Summary Judgment, Counterclaim, Contractual Terms, Implied Terms
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Quantum Meruit Summary Judgment Counterclaim Contractual Terms Implied Terms

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Kisumu Concrete Products Ltd

Plaintiff

Cementers Ltd

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 What were the terms of the contract for excavation works entered into between the Plaintiff and the Defendant?
  2. 2 Did the Plaintiff breach the contract or procure it through fraudulent misrepresentation?
  3. 3 Did the Defendant suffer any loss and damage as a result of the Plaintiff’s breach, and did the Defendant mitigate its losses?

Ratio Decidendi

The court found that the contract between the parties was clear, written, and did not contain any express terms regarding timelines or the Plaintiff’s capacity. The Defendant, having drafted the contract, could not seek to imply terms that were not included. Both parties contributed to delays in the project, and there was no evidence of fraudulent misrepresentation by the Plaintiff. The Plaintiff performed substantial work (over 87% of the contracted excavation), and payment was due for work done on a quantum meruit basis. The Defendant’s counterclaim for losses and penalties was unsupported by evidence and documentation. The Plaintiff was entitled to the claimed balance of Kshs.9,273,264...

Court Disposition

Plaintiff's claim allowed; Defendant's counterclaim dismissed.

Orders

  • The Defendant shall pay the Plaintiff Kshs.9,273,264 plus interest at 16% per annum from the date of filing suit to payment in full.
  • The Defendant shall pay the Plaintiff Kshs.5,109,588 with interest at 16% per annum from the date of filing suit to the date of payment.