[1995] KECA 126 (KLR)

[1995] KECA 126 (KLR)

The Court of Appeal held that the trial judge erred in granting the first respondent a set-off of retention money, as the contractual conditions for its payment had not been met at the relevant time. The letter of 17th August, 1973 constituted a certificate of practical completion, and the retention money could only...

Source-derived case information.

Citation
[1995] KECA 126 (KLR)
Parties
Appellant: Kisumu Municipal Council; Appellant: South British Insurance Co. Ltd; Respondent: BOT Construction (BETCO) Ltd; Respondent: Benjamin O. Tolo; Respondent: Joseph Ager; Respondent: Enosh Adongo
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 87 of 1988
Procedural Posture
Civil Appeal / Judgment
Outcome
First appellant's appeal partially allowed; second appellant's appeal dismissed.
Legal Topics
Building Contracts, Surety Bonds, Damages Assessment, Set Offs, Liquidated Damages
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Surety Bonds Damages Assessment Set Offs Liquidated Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Kisumu Municipal Council

Appellant

South British Insurance Co. Ltd

Appellant

BOT Construction (BETCO) Ltd

Respondent

Benjamin O. Tolo

Respondent

Joseph Ager

Respondent

Enosh Adongo

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the trial judge erred in failing to award the first appellant damages for completion of road works by another contractor after the first respondent's default.
  2. 2 Whether the set-off of retention money claimed by the first respondent was valid and properly granted by the trial court.
  3. 3 Whether the second appellant was entitled to recover from the respondents the amount paid under the surety bond.

Ratio Decidendi

The Court of Appeal held that the trial judge erred in granting the first respondent a set-off of retention money, as the contractual conditions for its payment had not been met at the relevant time. The letter of 17th August, 1973 constituted a certificate of practical completion, and the retention money could only be paid after the defects liability period or upon certification of making good defects. The first appellant was entitled to damages for the cost of completing the road works and reasonable compensation for inconvenience, as assessed by the trial judge. However, the set-off exceeded the appellant's entitlement and was not properly granted. Regarding the surety bond, the second...

Court Disposition

First appellant's appeal partially allowed; second appellant's appeal dismissed.

Orders

  • Set-off of Kshs 56,332.50 in favour of the first respondent is set aside.
  • Judgment of Kshs 37,604.50 in favour of the first appellant against the first respondent is sustained.