[2017] KEHC 5206 (KLR)

[2017] KEHC 5206 (KLR)

The court found that the Defendant failed to discharge the burden of proving timely completion of the works, as no completion certificate was issued and the Defendant's assertion of completion by April 2012 was unsupported. The Plaintiff was entitled to the contractual penalty for delay as stipulated in the...

Source-derived case information.

Citation
[2017] KEHC 5206 (KLR)
Parties
Plaintiff: Kisumu Steel Company Limited; Defendant: Arvind Engineering Limited
Court
High Court
Court Station
High Court at Kisumu
Jurisdiction
Kenya
Case Number
Civil Suit 1 of 2014
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Plaintiff for Kshs.3,012,262, with interest from the date of judgment. Defendant's counterclaim allowed and set off. Plaintiff awarded costs.
Judges
EM Muchoki
Legal Topics
Construction Contracts, Contractual Penalties, Burden of Proof, Counterclaims, Damages Assessment
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Contractual Penalties Burden of Proof Counterclaims Damages Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Kisumu Steel Company Limited

Plaintiff

Arvind Engineering Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was delay in completion of the works and if so whether the Plaintiff is entitled to the sum claimed as a penalty for the delay.
  2. 2 Whether the delay occasioned loss to the Plaintiff and whether the Plaintiff is entitled to the sums claimed for loss of profits.
  3. 3 Whether the works met the agreed specifications and if not whether the Defendant was obligated to rectify the defects and whether the Plaintiff is entitled to the Kshs.2,000,000/= claimed for hire of a crane.

Ratio Decidendi

The court found that the Defendant failed to discharge the burden of proving timely completion of the works, as no completion certificate was issued and the Defendant's assertion of completion by April 2012 was unsupported. The Plaintiff was entitled to the contractual penalty for delay as stipulated in the agreement, amounting to Kshs.4,350,000. However, the court held that the Plaintiff could not recover both the penalty and loss of profits for the same period, as the penalty was intended to compensate for such losses, and the Plaintiff's profit calculations were not sufficiently substantiated. The claim for crane hire was rejected due to lack of proof of payment and ambiguity as to...

Court Disposition

Judgment for the Plaintiff for Kshs.3,012,262, with interest from the date of judgment. Defendant's counterclaim allowed and set off. Plaintiff awarded costs.

Orders

  • Judgment entered for the Plaintiff against the Defendant for Kshs.3,012,262.
  • Interest awarded on the judgment sum from the date of judgment.