The court found that Kitololo Consultants Limited had proved, on a balance of probabilities, that it was orally contracted by the Managing Director of East Africa Portland Cement Company Limited to provide professional services for the Mill House Project. The plaintiff's evidence was uncontroverted as the defendant...

Source-derived case information.

Citation
[2019] KEHC 5434 (KLR)
Parties
Plaintiff: Kitololo Consultants Limited; Defendant: East Africa Portland Cement Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 210 of 2005
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff
Judges
MM Kasango
Legal Topics
Oral Contracts, Professional Fees, Burden of Proof, Public Procurement Regulations
Source Language
en
Commercial and Corporate Civil Procedure Oral Contracts Professional Fees Burden of Proof Public Procurement Regulations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Kitololo Consultants Limited

Plaintiff

East Africa Portland Cement Company Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether Kitololo Consultants Limited was orally contracted by East Africa Portland Cement Company Limited to provide professional services for the Mill House Project.
  2. 2 Whether Kitololo Consultants Limited is entitled to payment of Kshs. 4,238,620 as professional fees for services rendered.
  3. 3 Whether the alleged non-compliance with public procurement regulations by the defendant constitutes a valid defence to the plaintiff's claim.

Ratio Decidendi

The court found that Kitololo Consultants Limited had proved, on a balance of probabilities, that it was orally contracted by the Managing Director of East Africa Portland Cement Company Limited to provide professional services for the Mill House Project. The plaintiff's evidence was uncontroverted as the defendant failed to adduce any evidence in support of its defence. The court rejected the defendant's argument that non-compliance with public procurement regulations constituted a valid defence, holding that the obligation to comply with such regulations rested solely with the defendant and could not be used to defeat the plaintiff's claim. The court further found no evidence that the...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment is entered for Kitololo Consultants Limited for Kshs. 4,238,620 plus interest at court rate from the date of filing suit until payment in full.
  • Kitololo Consultants Limited is awarded costs of the suit.