[2011] KEHC 1502 (KLR)

[2011] KEHC 1502 (KLR)

The court held that the plaintiff failed to invoke the proper procedure by not filing a request for review before the Public Procurement Review Board within the statutory period. The dispute did not fall within the exceptions under Section 93 of the Act that would allow the High Court to exercise original...

Source-derived case information.

Citation
[2011] KEHC 1502 (KLR)
Parties
Plaintiff: Knots Construction Limited; Defendant: The Board of Governors Michuki Technical Training Institute; Defendant: Corban Construction Limited
Court
High Court
Court Station
High Court at Nyeri
Jurisdiction
Kenya
Case Number
Civil Case 87 of 2011
Procedural Posture
Civil Case / Ruling on Preliminary Objection
Outcome
suit and motion struck out with costs to the defendants
Judges
JK Sergon
Legal Topics
Public Procurement, Tender Disputes, Judicial Review, Contract Award Challenges
Source Language
en
Commercial and Corporate Administrative Law Public Procurement Tender Disputes Judicial Review Contract Award Challenges

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2
Sign in to unlock

Parties

Knots Construction Limited

Plaintiff

The Board of Governors Michuki Technical Training Institute

Defendant

Corban Construction Limited

Defendant

Procedural Posture

Civil Case / Ruling on Preliminary Objection

  1. 1 Whether the High Court has jurisdiction to entertain the suit in light of the Public Procurement and Disposal Act and Regulations.
  2. 2 Whether the plaintiff was required to exhaust the review process before the Public Procurement Review Board before approaching the court.
  3. 3 Whether the suit is competent given that a contract had already been executed between the defendants.

Ratio Decidendi

The court held that the plaintiff failed to invoke the proper procedure by not filing a request for review before the Public Procurement Review Board within the statutory period. The dispute did not fall within the exceptions under Section 93 of the Act that would allow the High Court to exercise original jurisdiction. The execution of a contract between the defendants further ousted the court's jurisdiction to re-open the tendering process. The court found the preliminary objection meritorious and struck out the suit and motion with costs to the defendants.

Court Disposition

suit and motion struck out with costs to the defendants

Orders

  • The preliminary objection is upheld.
  • The suit and the Notice of Motion are struck out with costs to the defendants.