[2018] KEELC 3759 (KLR)

[2018] KEELC 3759 (KLR)

The court found that while the applicant had paid the principal sums under the agreement, she had not cleared the interest element, which was not contested. The clearance letter relied upon by the applicant was issued erroneously by an unauthorized person. The applicant failed to demonstrate that water had been...

Source-derived case information.

Citation
[2018] KEELC 3759 (KLR)
Parties
Plaintiff: Kokonya Roselyn; Defendant: Tofina Rom Builders; Defendant: Unknown (Second Respondent, owner of LR No. 330/289)
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 54 of 2018
Procedural Posture
Injunction Application / Ruling on Interlocutory Applications
Outcome
applications dismissed with costs to the respondents
Legal Topics
Injunctive Relief, Possession Disputes, Arbitration Clauses, Utility Disconnection
Source Language
en
Land and Property Civil Procedure Injunctive Relief Possession Disputes Arbitration Clauses Utility Disconnection

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Kokonya Roselyn

Plaintiff

Tofina Rom Builders

Defendant

Unknown (Second Respondent, owner of LR No. 330/289)

Defendant

Procedural Posture

Injunction Application / Ruling on Interlocutory Applications

  1. 1 Whether the plaintiff is entitled to an injunction restraining the defendants from evicting or interfering with her possession of the suit property pending arbitration.
  2. 2 Whether the plaintiff is entitled to a mandatory injunction for reconnection of water and electricity utilities to the suit property.
  3. 3 Whether the plaintiff has fulfilled all her obligations under the agreement to warrant the reliefs sought.

Ratio Decidendi

The court found that while the applicant had paid the principal sums under the agreement, she had not cleared the interest element, which was not contested. The clearance letter relied upon by the applicant was issued erroneously by an unauthorized person. The applicant failed to demonstrate that water had been disconnected, and the circumstances surrounding the change of the electricity meter were unclear and not properly explained. The applicant, having not fulfilled all her obligations under the agreement, could not seek the court's protection through injunctive relief. The court held that a party cannot benefit from their own non-performance and that the applicant had not been candid...

Court Disposition

applications dismissed with costs to the respondents

Orders

  • The plaintiff's applications dated 8th February 2018 and 19th February 2018 are dismissed with costs to the respondents.
  • Any interim orders granted on 12th March 2018 are discharged.