[2001] KECA 292 (KLR)

[2001] KECA 292 (KLR)

The court found that the appellant failed to complete the contracted works within the agreed period and did not seek or obtain an extension of time as required by the contract. The evidence did not support the appellant's claims that the respondent made completion impossible or that force majeure applied, as the...

Source-derived case information.

Citation
[2001] KECA 292 (KLR)
Parties
Appellant: Kora Construction Company Ltd; Respondent: Mumias Sugar Company Ltd
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 22 of 2000
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed with costs
Judges
EO O'Kubasu
Legal Topics
Breach of Contract, Construction Contracts, Liquidated Damages, Frustration of Contract, Retention Fees
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Liquidated Damages Frustration of Contract Retention Fees

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Kora Construction Company Ltd

Appellant

Mumias Sugar Company Ltd

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the respondent made it impossible for the appellant to complete the contracted works in time.
  2. 2 Whether bad weather and the nature of the soil constituted force majeure justifying non-completion within the agreed period.
  3. 3 Whether the appellant was entitled to the claimed balance of contract price and damages for breach of contract.

Ratio Decidendi

The court found that the appellant failed to complete the contracted works within the agreed period and did not seek or obtain an extension of time as required by the contract. The evidence did not support the appellant's claims that the respondent made completion impossible or that force majeure applied, as the appellant was aware of the soil conditions before contracting and did not raise timely objections. The contract expressly prohibited adjustment of the contract sum except by mutual written agreement, and no such agreement was proved. The appellant was paid more than the value of certified completed works, and no evidence supported claims for additional works or retention fees. The...

Court Disposition

appeal dismissed with costs

Orders

  • The appeal is dismissed with costs to the respondent.