[2017] KEHC 9949 (KLR)

[2017] KEHC 9949 (KLR)

The court found that although the parties entered into a Payment Schedule Agreement on 17 June 2016 to resolve the dispute over Interim Certificate No. 21, subsequent correspondence and conduct evidenced a continuing dispute regarding incomplete works, penalties for delay, and additional claims. The Plaintiff...

Source-derived case information.

Citation
[2017] KEHC 9949 (KLR)
Parties
Plaintiff: Kore Forest Limited; Defendant: Totemic Construction Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 137 of 2016
Procedural Posture
Civil Case / Ruling on Interlocutory Applications and Referral to Arbitration
Outcome
Plaintiff's application dismissed as spent; Defendant's application for stay and referral to arbitration allowed, subject to parties attempting amicable settlement first; costs in the cause.
Judges
OA Sewe
Legal Topics
Arbitration Agreements, Interim Injunctions, Construction Contracts, Stay of Proceedings, Payment Disputes, Enforcement of Settlement
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Agreements Interim Injunctions Construction Contracts Stay of Proceedings Payment Disputes Enforcement of Settlement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Kore Forest Limited

Plaintiff

Totemic Construction Company Limited

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Applications and Referral to Arbitration

  1. 1 Whether the dispute between the parties is capable of being referred to arbitration under Clause 45 of the Construction Agreement.
  2. 2 Whether the Payment Schedule Agreement dated 17 June 2016 resolved all issues between the parties or if a live dispute remains.
  3. 3 Whether interim relief by way of injunction is tenable after the handover of the project site.

Ratio Decidendi

The court found that although the parties entered into a Payment Schedule Agreement on 17 June 2016 to resolve the dispute over Interim Certificate No. 21, subsequent correspondence and conduct evidenced a continuing dispute regarding incomplete works, penalties for delay, and additional claims. The Plaintiff suspended payments citing incomplete works and other outstanding issues, while the Defendant counterclaimed for unpaid sums. The court held that the existence of these unresolved issues constituted a live dispute under the Construction Agreement's arbitration clause. Consequently, the matter was suitable for referral to arbitration as provided by Section 6(1) of the Arbitration Act....

Court Disposition

Plaintiff's application dismissed as spent; Defendant's application for stay and referral to arbitration allowed, subject to parties attempting amicable settlement first; costs in the cause.

Orders

  • The Plaintiff's Notice of Motion dated 20 April 2016 is dismissed with no order as to costs.
  • The Defendant's Notice of Motion dated 29 April 2016 is allowed to the extent that the dispute is referred to arbitration, subject to the parties first reviewing the Payment Schedule Agreement and attempting amicable settlement pursuant to Clause 45.4 of the Construction Agreement.