[2025] KEHC 3389 (KLR)

[2025] KEHC 3389 (KLR)

The court found that the contract in question involved procurement by a public entity using public funds, and thus the Public Procurement and Asset Disposal Act and Article 227 of the Constitution were applicable and mandatory. The variations to the contract were not approved in accordance with statutory...

Source-derived case information.

Citation
[2025] KEHC 3389 (KLR)
Parties
Applicant: Koto Housing Kenya Limited; Respondent: Board of Governors Nairobi Technical Training Institute
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Arbitration Cause E020 of 2024
Procedural Posture
Arbitration Cause / Ruling on Applications to Set Aside and Enforce Arbitral Award
Outcome
Application to set aside the arbitral award allowed; application to enforce the award dismissed; no order as to costs.
Judges
BK Njoroge
Legal Topics
Public Procurement, Arbitral Award Enforcement, Contract Variation, Public Policy Exception, Statutory Compliance, Setting Aside Award
Source Language
en
Commercial and Corporate Administrative Law Public Procurement Arbitral Award Enforcement Contract Variation Public Policy Exception Statutory Compliance Setting Aside Award

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Koto Housing Kenya Limited

Applicant

Board of Governors Nairobi Technical Training Institute

Respondent

Procedural Posture

Arbitration Cause / Ruling on Applications to Set Aside and Enforce Arbitral Award

  1. 1 Whether the arbitral award contravenes public policy of Kenya as to warrant being set aside.
  2. 2 Whether the Court should set aside or adopt the arbitral award.

Ratio Decidendi

The court found that the contract in question involved procurement by a public entity using public funds, and thus the Public Procurement and Asset Disposal Act and Article 227 of the Constitution were applicable and mandatory. The variations to the contract were not approved in accordance with statutory requirements: there was no written approval by the procuring entity, no review by the evaluation committee, and no evidence that additional funding was secured and committed prior to the variation. The court held that the law could not be waived or excluded by contract, and that failure to comply with the Act and the Constitution rendered the contract variations and the resulting arbitral...

Court Disposition

Application to set aside the arbitral award allowed; application to enforce the award dismissed; no order as to costs.

Orders

  • The arbitral award of Mr. Christopher K. Kihara published on 31st January 2024 but delivered on 15th February 2024 is set aside.
  • No orders as to costs for either party.