[2024] KEELC 483 (KLR)

[2024] KEELC 483 (KLR)

The court found that the Plaintiffs established a violation of their right to a clean and healthy environment due to the 1st Defendant's construction of a wall only one meter from a seasonal river, contrary to environmental regulations and best practices. The proximity of the slaughterhouse to the stream posed a...

Source-derived case information.

Citation
[2024] KEELC 483 (KLR)
Parties
Plaintiff: John Lagat; Plaintiff: Robert Langat; Plaintiff: Kenneth Kosimbei; Plaintiff: Cyrus Kilonzi; Plaintiff: Jefy Rono; Plaintiff: Prof. Edward Tanui; Defendant: Naftali Kaberu; Defendant: National Environment Management Authority (NEMA)
Court
Environment and Land Court
Court Station
Environment and Land Court at Nakuru
Jurisdiction
Kenya
Case Number
Environment & Land Case 254 of 2015
Procedural Posture
Environment and Land Case / Judgment
Outcome
Plaintiffs partially succeed; orders granted for removal of wall, environmental testing, and possible closure; costs as per event.
Judges
A Ombwayo
Legal Topics
Environmental Impact Assessment, Public Participation, Right to Clean Environment, Riparian Reserves, Waste Management, Land Use Change
Source Language
en
Environmental Law Land and Property Environmental Impact Assessment Public Participation Right to Clean Environment Riparian Reserves Waste Management Land Use Change

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 13 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

John Lagat

Plaintiff

Robert Langat

Plaintiff

Kenneth Kosimbei

Plaintiff

Cyrus Kilonzi

Plaintiff

Jefy Rono

Plaintiff

Prof. Edward Tanui

Plaintiff

Naftali Kaberu

Defendant

National Environment Management Authority (NEMA)

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the 1st Defendant has violated the Plaintiffs. right to a clean and healthy environment.
  2. 2 Whether the 2nd Defendant's approval of the 1st Defendant's project was lawful and justified.
  3. 3 Whether the court has jurisdiction to determine the issues herein.

Ratio Decidendi

The court found that the Plaintiffs established a violation of their right to a clean and healthy environment due to the 1st Defendant's construction of a wall only one meter from a seasonal river, contrary to environmental regulations and best practices. The proximity of the slaughterhouse to the stream posed a risk of flooding, contamination, and environmental harm, as confirmed by expert reports and the court's site visit. The court held that public interest in environmental protection outweighed the 1st Defendant's private interests. The 2nd Defendant's approval of the project was found improper to the extent that it allowed construction so close to the river. The court ordered the...

Court Disposition

Plaintiffs partially succeed; orders granted for removal of wall, environmental testing, and possible closure; costs as per event.

Orders

  • The 1st Defendant shall remove the wall near the seasonal stream to a distance of 10 meters from the highest water mark within 30 days.
  • The 2nd Defendant (NEMA) shall test the liquid flowing from the slaughterhouse to the seasonal river and ascertain whether it is water or effluent; if effluent, corrective action must be taken or the slaughterhouse closed.