[2023] KEELC 20682 (KLR)

[2023] KEELC 20682 (KLR)

The court held that while the Biosafety Act does not expressly require strategic environmental assessment (SEA) or environmental and social impact assessment (ESIA) reports before the National Biosafety Authority (NBA) approves a GMO project, such reports and an Environmental Impact Assessment (EIA) licence from the...

Source-derived case information.

Citation
[2023] KEELC 20682 (KLR)
Parties
Applicant: Law Society of Kenya; Respondent: Attorney General; Respondent: National Biosafety Authority; Respondent: National Environment Management Authority; Respondent: Kenya Agricultural and Livestock Research Organization
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment and Planning Petition 2 of 2023
Procedural Posture
Environment and Planning Petition / Judgment
Outcome
petition dismissed
Judges
OA Angote
Legal Topics
Gmo Regulation, Environmental Impact Assessment, Public Participation, Right to Information, Precautionary Principle, Judicial Review
Source Language
en
Environmental Law Administrative Law Constitutional Law Gmo Regulation Environmental Impact Assessment Public Participation Right to Information Precautionary Principle +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 15 Party arguments 2
Sign in to unlock

Parties

Law Society of Kenya

Applicant

Attorney General

Respondent

National Biosafety Authority

Respondent

National Environment Management Authority

Respondent

Kenya Agricultural and Livestock Research Organization

Respondent

Procedural Posture

Environment and Planning Petition / Judgment

  1. 1 Whether after obtaining approval from the National Biosafety Authority a party could commence a project before obtaining an environmental impact assessment licence.
  2. 2 Whether it was mandatory for strategic environmental assessment and environmental and social impact assessment reports to be availed before the National Biosafety Authority could approve a project.
  3. 3 Whether a Cabinet Despatch was a statutory instrument subject to the Statutory Instruments Act.

Ratio Decidendi

The court held that while the Biosafety Act does not expressly require strategic environmental assessment (SEA) or environmental and social impact assessment (ESIA) reports before the National Biosafety Authority (NBA) approves a GMO project, such reports and an Environmental Impact Assessment (EIA) licence from the National Environment Management Authority (NEMA) are mandatory prerequisites before the commencement of any project, including trials or release to the market. The NBA's approval is a necessary first step, but no cultivation, importation, or release of genetically modified maize can lawfully begin without compliance with EIA requirements. The Cabinet Despatch lifting the GMO...

Court Disposition

petition dismissed

Orders

  • Petition dated January 16, 2023 is dismissed.
  • No order as to costs.