[2016] KEHC 8507 (KLR)

[2016] KEHC 8507 (KLR)

The court found that a valid contract existed between the parties, evidenced by the Local Service Order, tender documents, and correspondence, and that there was part-performance. The plaintiff was prevented from completing the work due to the defendant's actions, specifically the failure to release meters and...

Source-derived case information.

Citation
[2016] KEHC 8507 (KLR)
Parties
Plaintiff: Lawrence Mukora Muniu t/a Dynamite Civil Electrical Contractors; Defendant: Kamandura Tarambana Water Development Society
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 196 of 2012
Procedural Posture
Civil Suit / Judgment
Outcome
judgment for the plaintiff
Legal Topics
Breach of Contract, Liquidated Damages, Public Procurement, Interest Awards
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Liquidated Damages Public Procurement Interest Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Lawrence Mukora Muniu t/a Dynamite Civil Electrical Contractors

Plaintiff

Kamandura Tarambana Water Development Society

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a valid and binding contract between the parties.
  2. 2 Whether the defendant breached the contract by preventing the plaintiff from completing the work.
  3. 3 Whether the plaintiff is entitled to the unpaid contract balance and liquidated damages.

Ratio Decidendi

The court found that a valid contract existed between the parties, evidenced by the Local Service Order, tender documents, and correspondence, and that there was part-performance. The plaintiff was prevented from completing the work due to the defendant's actions, specifically the failure to release meters and facilitate completion, which constituted a breach by the defendant. The court held that the plaintiff was entitled to the value of the uncompleted work, calculated at Kshs. 530,000, and liquidated damages for a reasonable period (two weeks) at Kshs. 140,000, totaling Kshs. 670,000. The claim for interest at commercial rates was rejected for lack of proof, and only court rates were...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered for the plaintiff for Kshs. 670,000/-.
  • The sum awarded will attract interest at court rates from the date of judgment until payment in full.